3886 S CRENSHAW BLVD 90008

Certificate Information: 3886 S CRENSHAW BLVD 90008

Application / Permit
20016-10000-10626
Plan Check / Job No.
B20LA07915
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Bank
Work Description
Combine 3 tenants spaces and change of use from retail/restaurant to Credit Union branch office. Demolition of non bearing partitions & t-grid ceilings. New non bearing partitions, ceilings, furnishings, fixtures, and equipment.
Permit Issued
Issued on 6/18/2020
Issuing Office
Current Status
CofO Issued on 3/2/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/30/2020 APPLICANT
Assigned to Plan Check Engineer 5/7/2020 JOE VO
Corrections Issued 5/14/2020 JOE VO
Quality Review Completed 5/21/2020 PRANITA SHAH
Applicant returned to address corrections 6/10/2020 JOE VO
Plan Check Approved 6/16/2020 JOE VO
Issued 6/18/2020 APPLICANT
CofO in Progress 3/2/2021 LANNY MERRICK
CofO Issued 3/2/2021 ERNESTO CORRAL
Permit Finaled 3/2/2021 ERNESTO CORRAL

Permit Application Clearance Information

ZA Case Cleared 5/26/2020 ANACANY HURTADO
ZA Case Cleared 5/26/2020 ANACANY HURTADO
ZA Case Cleared 5/26/2020 ANACANY HURTADO
Specific Plan Cleared 6/9/2020 KYLE WINSTON
ZI Cleared 6/9/2020 KYLE WINSTON
Historic Resource Verification Cleared 6/10/2020 MICAELA TORRES-GIL
Redevelopment Project Area Cleared 6/11/2020 DAVID URITA
Sewer availability Cleared 6/11/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 6/12/2020 JEANIE LAM

Contact Information

Architect Moritz,, Mark Andrew; Lic. No.: C10159 881 CULEBRA ROAD      HILLSBOROUGH, CA 94010
Contractor Bremco Construction Inc; Lic. No.: 319444-B 3470 E SPRING ST      LONG BEACH, CA 90806

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 7/29/2020 Partial Approval LEOPOLDO MENDOZA
Wood Frame 7/29/2020 Partial Approval LEOPOLDO MENDOZA
Insulation 8/4/2020 Partial Approval LEOPOLDO MENDOZA
Wood Frame 8/4/2020 Partial Approval LEOPOLDO MENDOZA
Drywall Nailing 8/10/2020 Partial Approval LANNY MERRICK
T-Bar Ceiling 9/2/2020 Partial Inspection LEOPOLDO MENDOZA
T-Bar Ceiling 9/22/2020 Conditional Approval LEOPOLDO MENDOZA
Final 11/20/2020 Corrections Issued LEOPOLDO MENDOZA
Reinforced Masonry Frame 11/20/2020 Approved LEOPOLDO MENDOZA
SGSOV-Seismic Gas S/O Valve 11/20/2020 SGSOV Not Ready LEOPOLDO MENDOZA
Smoke Detectors 11/20/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Light Gage Steel Frame 12/17/2020 Approved TIMOTHY BUXTON
Drywall Nailing 1/6/2021 Approved LEOPOLDO MENDOZA
Final 2/26/2021 Partial Approval LANNY MERRICK
SGSOV-Seismic Gas S/O Valve 2/26/2021 SGSOV Approved LANNY MERRICK
Smoke Detectors 2/26/2021 Approved LANNY MERRICK