3933 N WEST POINT DR 90065
Certificate Information: 3933 N WEST POINT DR 90065
- Application / Permit
- 20016-10000-10517
- Plan Check / Job No.
- B20LA07802
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel (E) SFD, including removing an interior bearing wall and replacing a window with a new door. Addition of exterior wood deck.
- Permit Issued
- Issued on 10/8/2020
- Issuing Office
- Current Status
- Permit Finaled on 12/29/2020
Permit Application Status History
| Submitted | 4/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2020 | JESSE JIMENEZ |
| Corrections Issued | 5/6/2020 | JESSE JIMENEZ |
| Applicant returned to address corrections | 6/2/2020 | SINA KHOSRAVI |
| Applicant returned to address corrections | 6/23/2020 | HELEN NGUYEN |
| Applicant returned to address corrections | 8/26/2020 | ZAW HAN |
| Applicant returned to address corrections | 10/7/2020 | GEORGE ALVAREZ |
| Plan Check Approved | 10/8/2020 | RONALD ALLEN |
| Issued | 10/8/2020 | APPLICANT |
| Building Plans Picked Up | 10/13/2020 | APPLICANT |
| Permit Finaled | 12/28/2020 | ROBERT VORHIS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/12/2020 | EMIL KYUPELYAN |
| Roof/Waste drainage to street | Cleared | 6/15/2020 | EMIL KYUPELYAN |
| Specific Plan | Cleared | 8/21/2020 | NASHYA JENSEN |
| GPI Written Notices | Cleared | 10/8/2020 | JESSE JIMENEZ |
| Grading Pre-Inspection | Cleared | 10/8/2020 | GEORGE ALVAREZ |
Contact Information
| Contractor | Proenviro Construction Inc; Lic. No.: 911795-B | 3007 ROWENA AVE #2 LOS ANGELES, CA 90039 |
| Engineer | Yaprak,, Taskin Tolga; Lic. No.: C72927 | 708 SOUTH REDONDO AVE MANHATTAN BEACH, CA 90266 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/14/2020 | Corrections Issued | OSVALDO PARAMO |
| Wood Frame | 10/14/2020 | Partial Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 10/21/2020 | Approved | OSVALDO PARAMO |
| Wood Frame | 10/21/2020 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 11/9/2020 | Approved | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 11/9/2020 | Approved | OSVALDO PARAMO |
| Wood Frame | 11/9/2020 | Approved | OSVALDO PARAMO |
| Deck | 11/25/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Drywall Nailing | 11/25/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Insulation | 11/25/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Deck | 12/16/2020 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 12/16/2020 | Approved | OSVALDO PARAMO |
| Final | 12/16/2020 | Corrections Issued | OSVALDO PARAMO |
| Insulation | 12/16/2020 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 12/16/2020 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 12/16/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 12/28/2020 | Permit Finaled | ROBERT VORHIS |
| Smoke Detectors | 12/28/2020 | Approved | ROBERT VORHIS |