110 S FAIRFAX AVE A11 90036

Certificate Information: 110 S FAIRFAX AVE A11 90036

Application / Permit
20016-10000-10497
Plan Check / Job No.
B20LA07778
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
Proposed chage of use from retail to restaurant.
Permit Issued
Issued on 3/23/2021
Issuing Office
Current Status
CofO Issued on 10/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2020 APPLICANT
Assigned to Plan Check Engineer 5/22/2020 MICHAEL LOPEZ
Corrections Issued 5/28/2020 MICHAEL LOPEZ
Quality Review Completed 6/8/2020 QUAN NGHIEM
Building Plans Picked Up 6/15/2020 APPLICANT
Applicant returned to address corrections 7/27/2020 MICHAEL LOPEZ
Disabled Access Plans Picked Up 7/31/2020 APPLICANT
Plan Check Approved 2/2/2021 ZAW HAN
Issued 3/23/2021 APPLICANT
CofO in Progress 10/1/2021 KATY RAMIREZ
CofO Issued 10/1/2021 ERNESTO CORRAL
Permit Finaled 10/1/2021 ERNESTO CORRAL

Permit Application Clearance Information

"D" conditions Cleared 7/17/2020 ANACANY HURTADO
"Q" conditions Cleared 7/17/2020 ANACANY HURTADO
ZA Case Cleared 7/17/2020 ANACANY HURTADO
Fire Marshall Fire Life Safety Cleared 8/6/2020 ANDREW KO
DAS Clearance Cleared 8/10/2020 SHINE LIN
Eng Process Fee Ord 176,300 Cleared 9/29/2020 WALLIE JONG
Sewer availability Cleared 12/15/2020 WALLIE JONG
Food Service Establishment Cleared 1/21/2021 PAWAN VERMA
Food establishment approval Cleared 2/2/2021 LACDHS APPROVED

Contact Information

Contractor Pinhero Construction Inc; Lic. No.: 1009979-B 41541 DATE ST      MURRIETA, CA 92562
Engineer Chen,, Yeshen Jason; Lic. No.: C40169 20601 ALDA CT      WALNUT, CA 91789
Engineer Zhang,, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/19/2021 Conditional Approval TIMOTHY BUXTON
Wood Frame 6/24/2021 Approved TIMOTHY BUXTON
Drywall Nailing 7/6/2021 Approved TIMOTHY BUXTON
Wood Frame 7/6/2021 Approved TIMOTHY BUXTON
Drywall Nailing 7/7/2021 Approved TIMOTHY BUXTON
Excavation/Setback/Form/Re-Bar 7/8/2021 Approved TIMOTHY BUXTON
Grading Pre-Inspection 7/8/2021 Approved TIMOTHY BUXTON
T-Bar Ceiling 8/9/2021 Not Ready for Inspection EDWIN GREGORYONA
Pre-Inspection 8/20/2021 Approved KATY RAMIREZ
T-Bar Ceiling 8/20/2021 Partial Inspection KATY RAMIREZ
METHANE-Final 8/23/2021 Approved KATY RAMIREZ
METHANE-Rough 8/23/2021 Approved KATY RAMIREZ
Reinforced Masonry Frame 8/23/2021 Approved KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 8/23/2021 SGSOV Not Ready KATY RAMIREZ
Smoke Detectors 8/23/2021 Not Ready for Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 8/30/2021 SGSOV Not Ready KATY RAMIREZ
Smoke Detectors 8/30/2021 Not Ready for Inspection KATY RAMIREZ
Final 9/16/2021 No Access for Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 9/16/2021 SGSOV Not Ready KATY RAMIREZ
Smoke Detectors 9/16/2021 Not Ready for Inspection KATY RAMIREZ
Final 9/17/2021 Not Ready for Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 9/17/2021 SGSOV No Gas KATY RAMIREZ
Smoke Detectors 9/17/2021 Approved KATY RAMIREZ
Special/Order Compliance 9/20/2021 Approved KATY RAMIREZ
Special/Order Compliance 9/24/2021 Approved KATY RAMIREZ
Final 10/1/2021 OK to Issue CofO KATY RAMIREZ