ePlan ADU conversion. Convert Existing detached garage to Accessory Dwelling Unit per State Law
Permit Issued
Issued on 4/22/2021
Issuing Office
Current Status
CofO Issued on 4/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/3/2020 APPLICANT
Assigned to Plan Check Engineer 5/7/2020 VU NGUYEN
Corrections Issued 5/12/2020 VU NGUYEN
Quality Review Completed 5/14/2020 TU HUA
Applicant returned to address corrections 10/21/2020 VU NGUYEN
Applicant returned to address corrections 4/12/2021 VU NGUYEN
Applicant returned to address corrections 4/13/2021 VU NGUYEN
Plan Check Approved 4/15/2021 VU NGUYEN
Issued 4/22/2021 APPLICANT
CofO in Progress 4/7/2023 LILIANA PORTILLO
Permit Finaled 4/11/2023 DEROLD HAUFF
Permit Finaled 4/11/2023 DEROLD HAUFF
CofO Issued 4/11/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/22/2020 JEANIE LAM
Sewer availability Cleared 9/22/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 9/24/2020 JEANIE LAM
Community Plan Implem. Overlay Cleared 3/6/2021 RAFAEL FONTES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/11/2021 Corrections Issued EUGENE CASSIDY
Deputy Drilled-In Anchors 9/9/2021 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 9/13/2021 Approved JOHN KLARIN
PLUMBING-Rough 9/28/2021 Approved HORACE FULTZ
BUILDING-Rough-Frame 11/8/2021 Approved SABAS ALONSO
ELECTRICAL-Rough 11/8/2021 Approved SABAS ALONSO
Green Building Rough 11/8/2021 Approved SABAS ALONSO
Insulation 11/8/2021 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 11/8/2021 Approved SABAS ALONSO
Insulation 11/17/2021 Approved JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 11/29/2021 Corrections Issued SHAVONNE ESPINOZA
Drywall Nailing 12/2/2021 Partial Inspection JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 12/2/2021 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 12/2/2021 Partial Approval JUSTIN HAWLEY
HVAC-Rough 12/10/2021 Partial Inspection DONALD CRICHLOW
Drywall Nailing 12/16/2021 Partial Approval SHAVONNE ESPINOZA
Pre-Inspection 12/27/2021 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 5/19/2022 Corrections Issued LILIANA PORTILLO
Final 12/15/2022 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 12/15/2022 SGSOV No Gas LILIANA PORTILLO
Smoke Detectors 12/15/2022 Approved LILIANA PORTILLO
Final 1/6/2023 Corrections Issued LILIANA PORTILLO
Final 1/7/2023 Off-Hour Fees Due
Final 2/3/2023 Not Ready for Inspection LILIANA PORTILLO
Final 2/11/2023 Off-Hour Fees Due
Final 3/13/2023 Not Ready for Inspection JOSEPH MCGARRY
Final 3/18/2023 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Final 3/31/2023 Approved LILIANA PORTILLO
Final 3/31/2023 Conditional Approval LILIANA PORTILLO
HVAC-Final 3/31/2023 Approved LILIANA PORTILLO
PLUMBING-Final 3/31/2023 Approved LILIANA PORTILLO