2245 N HANCOCK ST 90031
Certificate Information: 2245 N HANCOCK ST 90031
- Application / Permit
- 20016-10000-10481
- Plan Check / Job No.
- B20LA07760
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO ADU AT REAR OF LOT.
- Permit Issued
- Issued on 8/17/2020
- Issuing Office
- Current Status
- CofO Issued on 1/23/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/30/2020 | JOE VO |
| Corrections Issued | 5/8/2020 | JOE VO |
| Quality Review Completed | 5/21/2020 | PRANITA SHAH |
| Plan Check Approved | 8/13/2020 | JOE VO |
| Issued | 8/17/2020 | APPLICANT |
| CofO in Progress | 1/12/2021 | CRAIG VAUGHAN |
| Permit Finaled | 1/23/2021 | DEROLD HAUFF |
| CofO Issued | 1/23/2021 | DEROLD HAUFF |
| Permit Finaled | 1/23/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/3/2020 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 6/3/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 6/4/2020 | CECILIO NAVARRO |
| HPOZ | Cleared | 7/29/2020 | JONATHAN KAPLAN |
| ZI | Cleared | 7/29/2020 | JONATHAN KAPLAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shagirian,, Ashot; Lic. No.: NA79415 | , |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/18/2020 | Partial Approval | RUBEN SALAS |
| ELECTRICAL-Rough | 9/24/2020 | Partial Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 10/1/2020 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Green Building Rough | 10/8/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2020 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 10/23/2020 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 10/23/2020 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 10/23/2020 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 10/28/2020 | Approved | OSVALDO PARAMO |
| Green Building Rough | 10/28/2020 | Approved | OSVALDO PARAMO |
| Insulation | 10/29/2020 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 11/5/2020 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 11/5/2020 | Approved | OSVALDO PARAMO |
| Final | 12/10/2020 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 12/10/2020 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 12/10/2020 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 12/10/2020 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 12/15/2020 | Approved | CRAIG VAUGHAN |
| Final | 12/15/2020 | Conditional Approval | CRAIG VAUGHAN |
| HVAC-Final | 12/15/2020 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 12/15/2020 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 12/15/2020 | SGSOV Approved | CRAIG VAUGHAN |