2245 N HANCOCK ST 90031

Certificate Information: 2245 N HANCOCK ST 90031

Application / Permit
20016-10000-10481
Plan Check / Job No.
B20LA07760
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO ADU AT REAR OF LOT.
Permit Issued
Issued on 8/17/2020
Issuing Office
Current Status
CofO Issued on 1/23/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2020 APPLICANT
Assigned to Plan Check Engineer 4/30/2020 JOE VO
Corrections Issued 5/8/2020 JOE VO
Quality Review Completed 5/21/2020 PRANITA SHAH
Plan Check Approved 8/13/2020 JOE VO
Issued 8/17/2020 APPLICANT
CofO in Progress 1/12/2021 CRAIG VAUGHAN
Permit Finaled 1/23/2021 DEROLD HAUFF
CofO Issued 1/23/2021 DEROLD HAUFF
Permit Finaled 1/23/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/3/2020 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 6/3/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 6/4/2020 CECILIO NAVARRO
Sewer availability Cleared 6/4/2020 CECILIO NAVARRO
HPOZ Cleared 7/29/2020 JONATHAN KAPLAN
ZI Cleared 7/29/2020 JONATHAN KAPLAN

Contact Information

Contractor Owner-Builder       ,
Engineer Shagirian,, Ashot; Lic. No.: NA79415       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/18/2020 Partial Approval RUBEN SALAS
ELECTRICAL-Rough 9/24/2020 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 10/1/2020 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 10/8/2020 Not Ready for Inspection OSVALDO PARAMO
Green Building Rough 10/8/2020 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 10/9/2020 Approved OSVALDO PARAMO
ELECTRICAL-Rough 10/23/2020 Approved OSVALDO PARAMO
HVAC-Rough 10/23/2020 Approved OSVALDO PARAMO
PLUMBING-Rough 10/23/2020 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 10/28/2020 Approved OSVALDO PARAMO
Green Building Rough 10/28/2020 Approved OSVALDO PARAMO
Insulation 10/29/2020 Approved OSVALDO PARAMO
Drywall Nailing 11/5/2020 Approved OSVALDO PARAMO
Interior/Exterior Lathing 11/5/2020 Approved OSVALDO PARAMO
Final 12/10/2020 Corrections Issued OSVALDO PARAMO
Green Building Final 12/10/2020 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 12/10/2020 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 12/10/2020 Approved OSVALDO PARAMO
ELECTRICAL-Final 12/15/2020 Approved CRAIG VAUGHAN
Final 12/15/2020 Conditional Approval CRAIG VAUGHAN
HVAC-Final 12/15/2020 Approved CRAIG VAUGHAN
PLUMBING-Final 12/15/2020 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 12/15/2020 SGSOV Approved CRAIG VAUGHAN