7737 W BECKETT ST 91042
Certificate Information: 7737 W BECKETT ST 91042
- Application / Permit
- 20016-10000-10406
- Plan Check / Job No.
- B20LA07667
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 366 S.F PORTION OF (E) 729 S.F GARAGE INTO A NEW ADU PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 6/2/2021
- Issuing Office
- Current Status
- CofO Issued on 1/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/1/2020 | FERNANDO FLORES |
| Corrections Issued | 5/4/2020 | FERNANDO FLORES |
| Applicant returned to address corrections | 6/25/2020 | RACHEL BEYENE |
| Applicant returned to address corrections | 7/17/2020 | ZAW HAN |
| Plan Check Approved | 8/4/2020 | ZAW HAN |
| Issued | 6/2/2021 | APPLICANT |
| Building Plans Picked Up | 6/9/2021 | APPLICANT |
| CofO in Progress | 1/4/2023 | DAVID ANDERSON |
| Permit Finaled | 1/18/2023 | MICHAEL SMITH |
| CofO Issued | 1/18/2023 | MICHAEL SMITH |
| Permit Finaled | 1/18/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/11/2020 | JEANIE LAM |
| Sewer availability | Cleared | 5/11/2020 | JEANIE LAM |
| Address approval | Cleared | 5/12/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 5/19/2020 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 7/22/2020 | PATRICK MISCHLICH |
Contact Information
| Contractor | Dhs Ventures Inc; Lic. No.: 1047699-B | 3575 CAHUENGA BLVD #350 LOS ANGELES, CA 90068 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/13/2021 | No Access for Inspection | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 7/16/2021 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 9/17/2021 | Approved | WILLIAM KUEHN |
| HVAC-Rough | 9/17/2021 | Approved | WILLIAM KUEHN |
| PLUMBING-Rough | 9/17/2021 | Approved | WILLIAM KUEHN |
| Wood Frame | 9/17/2021 | Approved | WILLIAM KUEHN |
| Insulation | 9/27/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 9/27/2021 | Approved | MATTHEW NELSON |
| Drywall Nailing | 10/7/2021 | Approved | WILLIAM WREN |
| Shower Pan | 10/7/2021 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 10/28/2021 | Approved | MATTHEW NELSON |
| Sewer | 11/9/2021 | Approved | WILLIAM KUEHN |
| Underground Mechanical | 11/9/2021 | Partial Inspection | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 2/7/2022 | No Access for Inspection | MATTHEW NELSON |
| Final | 2/7/2022 | No Access for Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 2/7/2022 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 2/7/2022 | No Access for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 2/10/2022 | Approved | DAVID MATSON |
| Final | 2/10/2022 | Corrections Issued | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 2/10/2022 | SGSOV Approved | DAVID MATSON |
| Smoke Detectors | 2/10/2022 | Approved | DAVID MATSON |
| Gas Test | 10/26/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Service/Power Release | 10/26/2022 | Corrections Issued | DAVID ANDERSON |
| Gas Test | 11/8/2022 | Approved | DAVID ANDERSON |
| Service/Power Release | 11/8/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 12/22/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 1/4/2023 | OK to Issue CofO | DAVID ANDERSON |