5388 E POPLAR BLVD 90032
Certificate Information: 5388 E POPLAR BLVD 90032
- Application / Permit
- 20016-10000-10374
- Plan Check / Job No.
- B20LA07632
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- EPLAN 4203 - Soft-Story seismic retrofit per LABC Chapter 93: Using two new columns
- Permit Issued
- Issued on 11/9/2020
- Issuing Office
- Current Status
- CofC Issued on 3/23/2021
Permit Application Status History
| Submitted | 4/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/27/2020 | JESSE VIDUYA |
| Corrections Issued | 6/4/2020 | JESSE VIDUYA |
| Quality Review Completed | 6/4/2020 | HANS SANTIAGO |
| Applicant returned to address corrections | 7/27/2020 | JESSE VIDUYA |
| Plan Check Approved | 8/5/2020 | JESSE VIDUYA |
| Issued | 11/9/2020 | APPLICANT |
| OK for CofC | 3/22/2021 | MARK FERRARI |
| CofC Issued | 3/23/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Construction near power lines | Cleared | 8/4/2020 | WALTER RAMIREZ |
| Tenant Habitability Plan | Cleared | 10/26/2020 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Cal Retrofit; Lic. No.: 1022167-B | 6900 CANBY AVE #108 RESEDA, CA 91335 |
| Engineer | Zohrevand,, Pedram; Lic. No.: C82328 | 21201 KITTRIDGE ST APT 9105 WOODLAND HILLS, CA 91303 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/13/2020 | Approved | MARK FERRARI |
| Deputy Drilled-In Anchors | 12/2/2020 | Conditional Approval | MARK FERRARI |
| Deputy Reinf. Concrete | 12/2/2020 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 12/8/2020 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 12/11/2020 | Approved | DARRYL ARNOLD |
| Structural Steel Frame | 12/11/2020 | Approved | DARRYL ARNOLD |
| Wood Frame | 12/11/2020 | Approved | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 12/16/2020 | Conditional Approval | MARK FERRARI |
| Wood Frame | 12/30/2020 | Corrections Issued | MARK FERRARI |
| Interior/Exterior Lathing | 2/18/2021 | Approved | MARK FERRARI |
| Final | 3/22/2021 | OK for CofC | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 3/22/2021 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 3/22/2021 | Approved | MARK FERRARI |