1974 S HOLT AVE 90034
Certificate Information: 1974 S HOLT AVE 90034
- Application / Permit
- 20016-10000-10371
- Plan Check / Job No.
- B20LA07629
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: INSTALL STEEL CANTILEVER COLUMN.
- Permit Issued
- Issued on 3/19/2021
- Issuing Office
- Current Status
- CofC Issued on 8/16/2021
Permit Application Status History
| Submitted | 4/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/14/2020 | HANS SANTIAGO |
| Corrections Issued | 5/20/2020 | HANS SANTIAGO |
| Quality Review Completed | 5/27/2020 | SAI KHUM |
| Plan Check Approved | 3/19/2021 | ANDREW SANTIAGO |
| Issued | 3/19/2021 | APPLICANT |
| OK for CofC | 8/16/2021 | GRANT WOODS |
| CofC Issued | 8/16/2021 | TED RIES |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 3/18/2021 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Cal - Quake Construction Inc; Lic. No.: 759817-B | 636 NORTH FORMOSA AVENUE LOS ANGELES, CA 90036 |
| Engineer | Labib,, Youhanna T; Lic. No.: NA4549 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/8/2021 | Approved | GRANT WOODS |
| Deputy Other (see comments) | 6/29/2021 | Conditional Approval | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 7/1/2021 | Approved | SORIN CIRSTOIU |
| Structural Steel Frame | 7/1/2021 | Partial Inspection | SORIN CIRSTOIU |
| Wood Frame | 7/1/2021 | Partial Inspection | SORIN CIRSTOIU |
| Deputy Wood Construction | 7/2/2021 | Conditional Approval | SORIN CIRSTOIU |
| Deputy Wood Construction | 7/8/2021 | Conditional Approval | PAUL DAVIDSON |
| Wood Frame | 7/9/2021 | Approved | DERRICK SPENCER |
| Drywall Nailing | 7/16/2021 | Approved | GRANT WOODS |
| Interior/Exterior Lathing | 7/28/2021 | Approved | GRANT WOODS |
| Final | 8/9/2021 | Partial Inspection | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 8/9/2021 | SGSOV Not Ready | GRANT WOODS |
| Smoke Detectors | 8/9/2021 | Approved | GRANT WOODS |
| Final | 8/16/2021 | OK for CofC | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 8/16/2021 | SGSOV Approved | GRANT WOODS |