10500 S VERMONT AVE 90044

Certificate Information: 10500 S VERMONT AVE 90044

Application / Permit
20016-10000-10368
Plan Check / Job No.
B20LA07626
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Soft-Story seismic retrofit per LABC Chapter 93: INSTALL STEEL CANTILEVER COLUMN AND PLYWOOD SHEAR WALL.
Permit Issued
Issued on 6/28/2021
Issuing Office
Current Status
CofC Issued on 8/24/2022

Permit Application Status History

Submitted 4/28/2020 APPLICANT
Assigned to Plan Check Engineer 5/27/2020 JESSE VIDUYA
Corrections Issued 6/4/2020 JESSE VIDUYA
Quality Review Completed 6/4/2020 HANS SANTIAGO
Applicant returned to address corrections 9/4/2020 JESSE VIDUYA
Plan Check Approved 9/15/2020 JESSE VIDUYA
Issued 6/28/2021 APPLICANT
OK for CofC 8/24/2022 DARRYL ARNOLD
CofC Issued 8/24/2022 WINSTON DUNNING

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 7/15/2020 SAM NAVID
Eng Process Fee Ord 176,300 Cleared 7/15/2020 ROSA SILVA
Community Plan Implem. Overlay Cleared 7/21/2020 RAFAEL FONTES
Tenant Habitability Plan Cleared 6/17/2021 MICHAEL SOTO

Contact Information

Contractor Braum Construction And Management; Lic. No.: 959860-B 6551 VAN NUYS BLVD, MEZZ FLOOR      VAN NUYS, CA 91401
Engineer Watson,, Darren S; Lic. No.: C87717 3704 MIDVALE AVE 6      LOS ANGELES, CA 90034

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 6/30/2021 Conditional Approval DARRYL ARNOLD
Deputy Other (see comments) 7/23/2021 Approved JOEY BUCHANAN
Deputy Other (see comments) 7/26/2021 Conditional Approval DARRYL ARNOLD
Excavation/Setback/Form/Re-Bar 7/26/2021 Conditional Approval DARRYL ARNOLD
Structural Steel Frame 7/26/2021 Approved DARRYL ARNOLD
Deputy Wood Construction 8/5/2021 Conditional Approval DARRYL ARNOLD
Floor/Roof Diaphrgm/Shear Wall 8/24/2021 Corrections Issued JOEY BUCHANAN
Structural Steel Frame 8/24/2021 Not Ready for Inspection JOEY BUCHANAN
Structural Steel Frame 8/26/2021 Conditional Approval DARRYL ARNOLD
Wall Anchors 8/26/2021 Corrections Issued DARRYL ARNOLD
Deputy Drilled-In Anchors 8/30/2021 Approved JOEY BUCHANAN
Deputy Wood Construction 8/30/2021 Approved JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 9/2/2021 Not Ready for Inspection DARRYL ARNOLD
Wall Anchors 9/2/2021 Approved DARRYL ARNOLD
Floor/Roof Diaphrgm/Shear Wall 9/3/2021 Conditional Approval DARRYL ARNOLD
Deputy Wood Construction 9/7/2021 Conditional Approval MARK FERRARI
Interior/Exterior Lathing 10/1/2021 Conditional Approval DARRYL ARNOLD
Final 10/28/2021 Not Ready for Inspection MARK FERRARI
SGSOV-Seismic Gas S/O Valve 10/28/2021 SGSOV Not Ready MARK FERRARI
Smoke Detectors 10/28/2021 Not Ready for Inspection MARK FERRARI
Final 11/23/2021 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 11/23/2021 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 11/23/2021 Conditional Approval DARRYL ARNOLD
Final 1/11/2022 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 1/11/2022 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 1/11/2022 Conditional Approval DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 8/22/2022 SGSOV Approved DARRYL ARNOLD
Final 8/24/2022 OK for CofC DARRYL ARNOLD
Smoke Detectors 8/24/2022 Approved DARRYL ARNOLD