7733 W BECKETT ST 91042

Certificate Information: 7733 W BECKETT ST 91042

Application / Permit
20016-10000-10333
Plan Check / Job No.
B20LA07607
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EXISTING 726 SQ FT GARAGE TO BE CONVERTED INTO A NEW STUDIO 366 SQ FT TO INCLUDE BEDROOM ARE, BATHROOM AND KITCHEN, LIVING ROOM. PROPOSED ADU GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 2/3/2021
Issuing Office
Metro
Current Status
CofO Issued on 1/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/19/2020 APPLICANT
Assigned to Plan Check Engineer 6/19/2020 RACHEL BEYENE
Corrections Issued 6/19/2020 RACHEL BEYENE
Plan Check Approved 7/23/2020 SERGIO GUTIERREZ
Building Plans Picked Up 7/23/2020 APPLICANT
Issued 2/3/2021 APPLICANT
CofO in Progress 12/23/2022 DAVID ANDERSON
CofO Issued 1/20/2023 MICHAEL SMITH
Permit Finaled 1/20/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/23/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 7/8/2020 GUILLERMO PETRA
Sewer availability Cleared 7/8/2020 GUILLERMO PETRA

Contact Information

Contractor Dhs Ventures Inc; Lic. No.: 1047699-B 3575 CAHUENGA BLVD #350      LOS ANGELES, CA 90068

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/9/2021 Partial Inspection BEAU COLLINS
Footing/Foundation/Slab 2/11/2021 Approved BEAU COLLINS
PLUMBING-Rough 2/11/2021 Partial Approval BEAU COLLINS
ELECTRICAL-Rough 3/11/2021 Corrections Issued BEAU COLLINS
PLUMBING-Rough 3/11/2021 Not Ready for Inspection BEAU COLLINS
Wood Frame 3/11/2021 Not Ready for Inspection BEAU COLLINS
ELECTRICAL-Rough 3/18/2021 Approved MATTHEW NELSON
PLUMBING-Rough 3/18/2021 Approved MATTHEW NELSON
Wood Frame 3/18/2021 Partial Approval MATTHEW NELSON
Insulation 3/22/2021 Not Ready for Inspection BEAU COLLINS
Insulation 3/30/2021 Approved BEAU COLLINS
Drywall Nailing 4/5/2021 No Access for Inspection BEAU COLLINS
Drywall Nailing 4/9/2021 Approved BEAU COLLINS
Interior/Exterior Lathing 4/29/2021 Approved BEAU COLLINS
PLUMBING-Rough 4/29/2021 Approved BEAU COLLINS
Shower Pan 5/4/2021 Approved MATTHEW NELSON
BUILDING-Rough-Frame 2/7/2022 No Access for Inspection MATTHEW NELSON
Final 2/7/2022 No Access for Inspection MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 2/7/2022 SGSOV Not Ready MATTHEW NELSON
Smoke Detectors 2/7/2022 No Access for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 2/9/2022 Approved MATTHEW NELSON
Final 2/9/2022 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 2/9/2022 SGSOV Not Ready MATTHEW NELSON
Smoke Detectors 2/9/2022 Not Ready for Inspection MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 10/18/2022 SGSOV Not Ready DAVID ANDERSON
Gas Test 10/26/2022 Not Ready for Inspection DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 10/26/2022 SGSOV Approved DAVID ANDERSON
Service/Power Release 10/26/2022 Corrections Issued DAVID ANDERSON
Gas Test 11/8/2022 Approved DAVID ANDERSON
Service/Power Release 11/8/2022 Not Ready for Inspection DAVID ANDERSON
Final 12/22/2022 OK to Issue CofO DAVID ANDERSON
Smoke Detectors 12/22/2022 Approved DAVID ANDERSON