8003 S DENROCK AVE 90045
Certificate Information: 8003 S DENROCK AVE 90045
- Application / Permit
- 20016-10000-10304
- Plan Check / Job No.
- B20LA07575
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan ADU. Convert existing 19'x19" detached garage to a new accessory dwelling unit
- Permit Issued
- Issued on 9/30/2020
- Issuing Office
- Current Status
- CofO Issued on 5/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/14/2020 | VU NGUYEN |
| Corrections Issued | 5/15/2020 | VU NGUYEN |
| Quality Review Completed | 5/21/2020 | TU HUA |
| Applicant returned to address corrections | 5/29/2020 | VU NGUYEN |
| Plan Check Approved | 9/24/2020 | VU NGUYEN |
| Issued | 9/30/2020 | APPLICANT |
| CofO in Progress | 4/19/2021 | BRENDAN LOONEY |
| CofO Issued | 5/6/2021 | VINCENT COTTON |
| Permit Finaled | 5/6/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Address approval | Cleared | 6/5/2020 | DINAH GARIN |
| Sewer availability | Cleared | 6/5/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/18/2020 | DINAH GARIN |
| Construction near power lines | Cleared | 8/25/2020 | WALTER RAMIREZ |
| Specific Plan | Cleared | 9/16/2020 | VALERIA CEJA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 11/17/2020 | Corrections Issued | JUAN VALENZUELA |
| PLUMBING-Rough | 11/17/2020 | Corrections Issued | JUAN VALENZUELA |
| Wood Frame | 11/17/2020 | Corrections Issued | JUAN VALENZUELA |
| PLUMBING-Rough | 12/4/2020 | Partial Approval | DAVID HEINE |
| Sewer | 12/4/2020 | Approved | DAVID HEINE |
| BUILDING-Rough-Frame | 12/11/2020 | Partial Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 12/11/2020 | Corrections Issued | JUAN VALENZUELA |
| METHANE-Rough | 12/11/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| PLUMBING-Rough | 12/11/2020 | Corrections Issued | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 12/24/2020 | Approved | DAVID HEINE |
| ELECTRICAL-Rough | 12/24/2020 | Approved | DAVID HEINE |
| Gas Test | 12/24/2020 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 12/24/2020 | Partial Approval | DAVID HEINE |
| METHANE-Rough | 12/24/2020 | Approved | DAVID HEINE |
| PLUMBING-Rough | 12/24/2020 | Approved | DAVID HEINE |
| Wood Frame | 12/24/2020 | Approved | DAVID HEINE |
| Insulation | 12/29/2020 | Approved | DAVID HEINE |
| Drywall Nailing | 1/13/2021 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 1/14/2021 | Approved | JUAN VALENZUELA |
| Shower Pan | 1/14/2021 | Corrections Issued | JUAN VALENZUELA |
| Shower Pan | 2/1/2021 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 2/4/2021 | Approved | JUAN VALENZUELA |
| Final | 3/26/2021 | Corrections Issued | ANTHONY MCDOWALL |
| SGSOV-Seismic Gas S/O Valve | 3/26/2021 | SGSOV Approved | ANTHONY MCDOWALL |
| Smoke Detectors | 3/26/2021 | Approved | ANTHONY MCDOWALL |
| Final | 4/8/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Final | 4/16/2021 | OK to Issue CofO | BRENDAN LOONEY |