5310 N NATICK AVE 91411
Certificate Information: 5310 N NATICK AVE 91411
- Application / Permit
- 20016-10000-10188
- Plan Check / Job No.
- B20LA07491
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan ADU conversion. Convert existing accessory building to detached ADU per state law GCS 65852.2(e)(1)(A). All works per Wood Frame Prescriptive Provisions. Fire sprinkler is provided throughout.
- Permit Issued
- Issued on 6/8/2020
- Issuing Office
- Current Status
- CofO Issued on 8/24/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/30/2020 | HELEN NGUYEN |
| Corrections Issued | 5/6/2020 | HELEN NGUYEN |
| Quality Review Completed | 5/14/2020 | PRANITA SHAH |
| Applicant returned to address corrections | 6/2/2020 | HELEN NGUYEN |
| Plan Check Approved | 6/5/2020 | HELEN NGUYEN |
| Issued | 6/8/2020 | APPLICANT |
| CofO in Progress | 8/7/2020 | CHRIS CHRISTENSEN |
| Permit Finaled | 8/24/2020 | MICHAEL SMITH |
| CofO Issued | 8/24/2020 | MICHAEL SMITH |
| Permit Finaled | 8/24/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/15/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 5/15/2020 | ADRIAN CASTRO |
| Construction within easement | Cleared | 5/28/2020 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 5/28/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 6/10/2020 | Partial Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 6/10/2020 | Partial Approval | THOMAS FINNILA |
| PLUMBING-Rough | 6/10/2020 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 6/12/2020 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 6/12/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2020 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 6/12/2020 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 6/12/2020 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2020 | Partial Approval | THOMAS FINNILA |
| Sewer | 6/15/2020 | Partial Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 6/16/2020 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 6/18/2020 | Approved | CHARLES POWELL |
| ELECTRICAL-Rough | 6/18/2020 | Approved | CHARLES POWELL |
| HVAC-Rough | 6/18/2020 | Approved | CHARLES POWELL |
| PLUMBING-Rough | 6/18/2020 | Approved | CHARLES POWELL |
| Shower Pan | 6/18/2020 | Approved | CHARLES POWELL |
| Insulation | 6/23/2020 | Approved | DANIEL DREW |
| Drywall Nailing | 7/1/2020 | Approved | CHARLES POWELL |
| Interior/Exterior Lathing | 7/1/2020 | Partial Approval | CHARLES POWELL |
| Drywall Nailing | 7/3/2020 | Conditional Approval | MATTHEW NUCKOLLS |
| Interior/Exterior Lathing | 7/3/2020 | Partial Approval | MATTHEW NUCKOLLS |
| Interior/Exterior Lathing | 7/6/2020 | Approved | DANIEL DREW |
| ELECTRICAL-Final | 7/22/2020 | Corrections Issued | CHARLES POWELL |
| Gas Test | 7/22/2020 | Approved | CHARLES POWELL |
| HVAC-Final | 7/22/2020 | Corrections Issued | CHARLES POWELL |
| PLUMBING-Final | 7/22/2020 | No Access for Inspection | CHARLES POWELL |
| SGSOV-Seismic Gas S/O Valve | 7/22/2020 | SGSOV Approved | CHARLES POWELL |
| Service/Power Release | 7/22/2020 | Corrections Issued | CHARLES POWELL |
| Smoke Detectors | 7/22/2020 | No Access for Inspection | CHARLES POWELL |
| ELECTRICAL-Final | 7/27/2020 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Final | 7/27/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Final | 7/27/2020 | Approved | MISAEL ESPARZA |
| Service/Power Release | 7/27/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 7/27/2020 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 8/3/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| Final | 8/3/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| HVAC-Final | 8/3/2020 | Approved | MICHAEL TEMPLE |
| Service/Power Release | 8/3/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| Drywall Nailing | 8/7/2020 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 8/7/2020 | Approved | CHRIS CHRISTENSEN |
| Final | 8/7/2020 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Service/Power Release | 8/7/2020 | Approved | CHRIS CHRISTENSEN |