2027 N VESTAL AVE 90026

Certificate Information: 2027 N VESTAL AVE 90026

Application / Permit
20016-10000-10183
Plan Check / Job No.
B20LA07487
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Soft-Story seismic retrofit per LABC Chapter 93: Install (2) special steel cantilever columns
Permit Issued
Issued on 9/10/2020
Issuing Office
Current Status
CofC Issued on 12/17/2020

Permit Application Status History

Submitted 4/23/2020 APPLICANT
Assigned to Plan Check Engineer 5/20/2020 DANIEL SANJUAN
Corrections Issued 6/3/2020 DANIEL SANJUAN
Quality Review Completed 6/5/2020 SAI KHUM
Plan Check Approved 8/14/2020 DANIEL SANJUAN
Issued 9/10/2020 APPLICANT
OK for CofC 12/15/2020 MARK FERRARI
CofC Issued 12/17/2020 ERNESTO CORRAL

Permit Application Clearance Information

Tenant Habitability Plan Cleared 9/8/2020 STEVEN HOFSTAD

Contact Information

Contractor Courteous Construction Co Inc; Lic. No.: 567324-B P O BOX 9287      GLENDALE, CA 91226
Engineer Rezazadeh,, Mehdi; Lic. No.: C49626 P O BOX 98      DANVILLE, CA 94526

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/23/2020 Approved MARK FERRARI
Wood Frame 9/29/2020 Not Ready for Inspection MARK FERRARI
Wood Frame 9/30/2020 Partial Approval MARK FERRARI
Deputy Steel/Welding 10/9/2020 Conditional Approval DARRYL ARNOLD
Deputy Drilled-In Anchors 10/14/2020 Approved MARK FERRARI
Footing/Foundation/Slab 10/14/2020 Approved MARK FERRARI
Structural Steel Frame 10/14/2020 Approved MARK FERRARI
Wood Frame 10/14/2020 Approved MARK FERRARI
Deputy Reinf. Concrete 10/16/2020 Conditional Approval MARK FERRARI
Interior/Exterior Lathing 10/30/2020 Approved MARK FERRARI
Final 11/12/2020 Corrections Issued MARK FERRARI
SGSOV-Seismic Gas S/O Valve 11/12/2020 SGSOV Not Ready MARK FERRARI
Smoke Detectors 11/12/2020 Approved MARK FERRARI
Final 12/2/2020 Corrections Issued MARK FERRARI
SGSOV-Seismic Gas S/O Valve 12/2/2020 SGSOV Not Ready MARK FERRARI
Final 12/15/2020 OK for CofC MARK FERRARI
SGSOV-Seismic Gas S/O Valve 12/15/2020 SGSOV Approved MARK FERRARI