5713 N NEWCASTLE AVE 91316

Certificate Information: 5713 N NEWCASTLE AVE 91316

Application / Permit
20016-10000-10178
Plan Check / Job No.
B20LA07481
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan ADU. Convert existing detached garage 23'X22' to ADU per state law 12.22 A.33(b)(5) ALL WORK PER WFPP
Permit Issued
Issued on 9/29/2020
Issuing Office
Current Status
CofO Issued on 12/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/24/2020 APPLICANT
Assigned to Plan Check Engineer 4/30/2020 MONICA RAMIREZ
Corrections Issued 5/6/2020 MONICA RAMIREZ
Quality Review Completed 5/14/2020 TU HUA
Applicant returned to address corrections 9/18/2020 MONICA RAMIREZ
Plan Check Approved 9/24/2020 MONICA RAMIREZ
Issued 9/29/2020 APPLICANT
CofO in Progress 10/28/2022 SEAN HAUPT
CofO Issued 12/22/2022 MICHAEL SMITH
Permit Finaled 12/22/2022 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 8/27/2020 RIDWAN HARDY
Address approval Cleared 9/1/2020 ADRIAN CASTRO
Sewer availability Cleared 9/1/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 9/11/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 10/14/2020 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 10/14/2020 Corrections Issued STEVEN BACK
PLUMBING-Rough 10/14/2020 Corrections Issued STEVEN BACK
Pre-Inspection 10/14/2020 Corrections Issued STEVEN BACK
Excavation/Setback/Form/Re-Bar 12/8/2020 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 12/8/2020 No Access for Inspection STEVEN BACK
Pre-Inspection 12/8/2020 Partial Approval STEVEN BACK
ELECTRICAL-Rough 2/1/2021 Corrections Issued STEVEN BACK
Excavation/Setback/Form/Re-Bar 2/1/2021 Corrections Issued STEVEN BACK
Insulation 2/1/2021 Not Ready for Inspection STEVEN BACK
PLUMBING-Rough 2/1/2021 Not Ready for Inspection STEVEN BACK
BUILDING-Rough-Frame 3/9/2021 Corrections Issued STEVEN BACK
Excavation/Setback/Form/Re-Bar 3/9/2021 Approved STEVEN BACK
Footing/Foundation/Slab 3/9/2021 Approved STEVEN BACK
BUILDING-Rough-Frame 3/12/2021 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 4/19/2021 Approved STEVEN BACK
Interior/Exterior Lathing 5/6/2021 Approved RYAN SALAZAR
HVAC-Rough 6/7/2021 Corrections Issued STEVEN BACK
PLUMBING-Rough 6/7/2021 Corrections Issued STEVEN BACK
Sewer 6/7/2021 Approved STEVEN BACK
ELECTRICAL-Rough 6/17/2021 Approved STEVEN BACK
PLUMBING-Rough 6/17/2021 Approved STEVEN BACK
Underground Mechanical 6/17/2021 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 6/21/2021 No Access for Inspection STEVEN BACK
Underground Mechanical 6/30/2021 Partial Approval STEVEN BACK
HVAC-Final 4/29/2022 Not Ready for Inspection DAVID SCANTLIN
HVAC-Rough 4/29/2022 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 5/27/2022 Approved SEAN HAUPT
Green Building Rough 5/27/2022 Approved SEAN HAUPT
HVAC-Rough 5/27/2022 Approved SEAN HAUPT
Drywall Nailing 7/8/2022 Approved MICHAEL SMITH
Final 10/25/2022 Corrections Issued SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 10/25/2022 SGSOV Not Ready SEAN HAUPT
Smoke Detectors 10/25/2022 Not Ready for Inspection SEAN HAUPT
Final 10/28/2022 OK to Issue CofO SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 10/28/2022 SGSOV Approved SEAN HAUPT
Smoke Detectors 10/28/2022 Approved SEAN HAUPT