545 N FULLER AVE 90036

Certificate Information: 545 N FULLER AVE 90036

Application / Permit
20016-10000-10149
Plan Check / Job No.
B20LA07454
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED REC ROOM/GARAGE TO ADU PER GCS 65852.2(e)(1)(A) 1 OF 2
Permit Issued
Issued on 8/20/2020
Issuing Office
Current Status
CofO Issued on 4/7/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/23/2020 APPLICANT
Assigned to Plan Check Engineer 5/14/2020 SERGIO GUTIERREZ
Corrections Issued 5/28/2020 SERGIO GUTIERREZ
Quality Review Completed 6/9/2020 KESETE HAREGOT
Building Plans Picked Up 6/16/2020 APPLICANT
Green Plans Picked Up 7/20/2020 APPLICANT
Applicant returned to address corrections 8/4/2020 SERGIO GUTIERREZ
Plan Check Approved 8/20/2020 SERGIO GUTIERREZ
Issued 8/20/2020 APPLICANT
CofO in Progress 4/6/2021 CHRIS CHRISTENSEN
Permit Finaled 4/7/2021 DEROLD HAUFF
CofO Issued 4/7/2021 DEROLD HAUFF
Permit Finaled 4/7/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/25/2020 RENZ SORIANO
Roof/Waste drainage to street Cleared 6/25/2020 RENZ SORIANO
Sewer availability Cleared 6/25/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 6/29/2020 RENZ SORIANO
Hydrant and Access approval Cleared 7/10/2020 KURT CORRAL
Green Code Cleared 7/20/2020 VIVIAN LAO

Contact Information

Contractor Trinity Builders & Design Inc; Lic. No.: 988119-B 7022 DARBY AVE UNIT A      RESEDA, CA 91335
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/5/2020 Partial Approval CHRIS CHRISTENSEN
Underground Mechanical 10/14/2020 Approved CHRIS CHRISTENSEN
Sewer 10/20/2020 Approved CHRIS CHRISTENSEN
Underground Mechanical 10/20/2020 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 10/28/2020 Conditional Approval CHRIS CHRISTENSEN
HVAC-Rough 10/28/2020 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 10/28/2020 Approved CHRIS CHRISTENSEN
Wood Frame 10/28/2020 Conditional Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 11/9/2020 Approved CHRIS CHRISTENSEN
Insulation 11/9/2020 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 11/9/2020 Approved CHRIS CHRISTENSEN
Shower Pan 11/9/2020 Approved CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 11/9/2020 Approved CHRIS CHRISTENSEN
Drywall Nailing 11/14/2020 Approved STUART CHAPMAN
Gas Test 11/14/2020 Approved STUART CHAPMAN
Final 3/22/2021 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 3/22/2021 Corrections Issued CHRIS CHRISTENSEN
METHANE-Final 3/22/2021 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 3/22/2021 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 3/22/2021 Approved CHRIS CHRISTENSEN
Final 4/5/2021 OK to Issue CofO CHRIS CHRISTENSEN