1708 S GARTH AVE 90035

Certificate Information: 1708 S GARTH AVE 90035

Application / Permit
20016-10000-10079
Plan Check / Job No.
B20LA07371
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) DETACHED ACCESSORY DWELLING UNIT PER ORDINANCE
Permit Issued
Issued on 4/12/2021
Issuing Office
Current Status
CofO Issued on 12/23/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/22/2020 APPLICANT
Assigned to Plan Check Engineer 5/6/2020 AMIR DANAI
Corrections Issued 5/19/2020 AMIR DANAI
Quality Review Completed 6/4/2020 ARMEN JIVALAGIAN
Green Plans Picked Up 10/2/2020 APPLICANT
Plan Check Approved 11/1/2020 AMIR DANAI
Issued 4/12/2021 APPLICANT
Building Plans Picked Up 4/14/2021 APPLICANT
CofO in Progress 12/21/2021 JUAN VALENZUELA
Permit Finaled 12/23/2021 KENNETH NAGLE
CofO Issued 12/23/2021 KENNETH NAGLE
Permit Finaled 12/23/2021 KENNETH NAGLE

Permit Application Clearance Information

Address approval Cleared 7/6/2020 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 7/6/2020 ELAINE LEI
Sewer availability Cleared 7/6/2020 ELAINE LEI
Low Impact Development Cleared 8/9/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 8/11/2020 ELAINE LEI
Hydrant and Access approval Cleared 9/15/2020 KURT CORRAL
Green Code Cleared 10/2/2020 DONALD CRICHLOW

Contact Information

Contractor Seagull Construction & Development; Lic. No.: 1073738-B 369 COLUMBIA AVE #433      LOS ANGELES, CA 90017
Engineer Boranian,, Paul Darian; Lic. No.: S5944 23261 BURBANK BL      WOODLAND HILLS, CA 91367

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/19/2021 Corrections Issued EVAN COOPER
Excavation/Setback/Form/Re-Bar 6/10/2021 Corrections Issued KEVIN SARGSYAN
METHANE-Subgrade 6/14/2021 Approved EVAN COOPER
PLUMBING-Rough 6/14/2021 Partial Approval EVAN COOPER
Sewer 6/14/2021 Approved EVAN COOPER
Excavation/Setback/Form/Re-Bar 6/17/2021 Conditional Approval EVAN COOPER
Footing/Foundation/Slab 6/17/2021 Conditional Approval EVAN COOPER
METHANE-Barrier 6/17/2021 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 6/22/2021 SGSOV Not Ready EVAN COOPER
Underground Mechanical 6/22/2021 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 7/8/2021 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 7/19/2021 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 7/23/2021 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 8/2/2021 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 8/6/2021 Partial Approval EVAN COOPER
PLUMBING-Rough 8/16/2021 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 8/24/2021 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 8/24/2021 Not Ready for Inspection EVAN COOPER
Gas Test 8/24/2021 Partial Approval EVAN COOPER
HVAC-Rough 8/24/2021 Not Ready for Inspection EVAN COOPER
METHANE-Rough 8/24/2021 Approved EVAN COOPER
PLUMBING-Rough 8/24/2021 Approved EVAN COOPER
Rough-Elec/Plmb/HVAC 8/24/2021 Partial Approval EVAN COOPER
Shower Pan 8/24/2021 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 8/27/2021 Partial Approval EVAN COOPER
HVAC-Rough 8/27/2021 Approved EVAN COOPER
BUILDING-Rough-Frame 9/9/2021 Approved EVAN COOPER
Green Building Rough 9/9/2021 Approved EVAN COOPER
Interior/Exterior Lathing 9/9/2021 Approved EVAN COOPER
Verify Sprinkler Sign Off 9/9/2021 Approved EVAN COOPER
Wood Frame 9/9/2021 Approved EVAN COOPER
Insulation 9/13/2021 Partial Approval EVAN COOPER
Drywall Nailing 9/27/2021 Approved EVAN COOPER
Insulation 9/27/2021 Approved EVAN COOPER
Interior/Exterior Lathing 10/8/2021 Approved EVAN COOPER
Gas Test 11/12/2021 Approved DEANDRE HOFFMAN
ELECTRICAL-Final 11/18/2021 Corrections Issued STEPHANIE SWANSON
PLUMBING-Final 11/18/2021 Approved STEPHANIE SWANSON
Smoke Detectors 11/18/2021 Corrections Issued STEPHANIE SWANSON
HVAC-Final 11/19/2021 Approved KENNETH NAGLE
ELECTRICAL-Final 12/3/2021 Approved EVAN COOPER
Final 12/3/2021 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 12/3/2021 Approved EVAN COOPER
Green Building Final 12/3/2021 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 12/3/2021 SGSOV Approved EVAN COOPER
Service/Power Release 12/3/2021 Not Ready for Inspection EVAN COOPER
Smoke Detectors 12/3/2021 Approved EVAN COOPER
Final 12/14/2021 Conditional Approval EVAN COOPER
Service/Power Release 12/14/2021 Approved EVAN COOPER