4425 W MAPLEWOOD AVE 90004
Certificate Information: 4425 W MAPLEWOOD AVE 90004
- Application / Permit
- 20016-10000-09998
- Plan Check / Job No.
- B20LA07300
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- EPLAN 3888 - Soft-Story seismic retrofit per LABC Chapter 93: INSTALL (6) STEEL CANTILEVER COLUMNS.
- Permit Issued
- Issued on 10/2/2020
- Issuing Office
- Current Status
- CofC Issued on 3/1/2021
Permit Application Status History
| Submitted | 4/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2020 | JESSE VIDUYA |
| Corrections Issued | 5/28/2020 | JESSE VIDUYA |
| Quality Review Completed | 6/1/2020 | SAI KHUM |
| Plan Check Approved | 7/28/2020 | JESSE VIDUYA |
| Issued | 10/2/2020 | APPLICANT |
| OK for CofC | 2/19/2021 | MARK FERRARI |
| CofC Issued | 3/1/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 10/2/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Optimum Seismic Inc; Lic. No.: 1012702-B | 5508 S SANTA FE AVENUE VERNON, CA 90058 |
| Engineer | Park,, Kenan; Lic. No.: C86314 | 904 S HARVARD BLVD APT 208 LOS ANGELES, CA 90006 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/6/2020 | Corrections Issued | MARK FERRARI |
| Wood Frame | 10/13/2020 | Partial Approval | MARK FERRARI |
| Wood Frame | 11/18/2020 | Corrections Issued | JONATHAN QUACH |
| Deputy Wood Construction | 11/25/2020 | Conditional Approval | MARK FERRARI |
| Deputy Drilled-In Anchors | 12/2/2020 | Conditional Approval | JONATHAN QUACH |
| Deputy Other (see comments) | 12/2/2020 | Conditional Approval | JONATHAN QUACH |
| Footing/Foundation/Slab | 12/4/2020 | Approved | MARK FERRARI |
| Structural Steel Frame | 12/4/2020 | Approved | MARK FERRARI |
| Wood Frame | 12/4/2020 | Approved | MARK FERRARI |
| Deputy Other (see comments) | 12/8/2020 | Conditional Approval | JONATHAN QUACH |
| Deputy Reinf. Concrete | 12/8/2020 | Conditional Approval | JONATHAN QUACH |
| Interior/Exterior Lathing | 12/30/2020 | Approved | JONATHAN QUACH |
| Final | 2/19/2021 | OK for CofC | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 2/19/2021 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 2/19/2021 | Approved | MARK FERRARI |