3755 1/2 N LOCKE AVE 90032

Certificate Information: 3755 1/2 N LOCKE AVE 90032

Application / Permit
20016-10000-09971
Plan Check / Job No.
B20LA07270
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
(E) 2-car garage convert to one ADU PER GCS 65852.2(e)(1)(C) FOR EXISTING MULTI-FAMILY
Permit Issued
Issued on 11/19/2020
Issuing Office
Current Status
CofO Issued on 11/29/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/23/2020 APPLICANT
Assigned to Plan Check Engineer 5/14/2020 JESSE ARELLANO
Corrections Issued 5/21/2020 JESSE ARELLANO
Quality Review Completed 5/27/2020 BILL STUTSMAN
Building Plans Picked Up 5/27/2020 APPLICANT
Applicant returned to address corrections 7/15/2020 JESSE ARELLANO
Applicant returned to address corrections 8/22/2020 JESSE ARELLANO
Applicant returned to address corrections 9/8/2020 JESSE ARELLANO
Plan Check Approved 9/18/2020 JESSE ARELLANO
Issued 11/19/2020 APPLICANT
CofO in Progress 11/29/2021 ERNESTO CORRAL
Permit Finaled 11/29/2021 ERNESTO CORRAL
CofO Issued 11/29/2021 ERNESTO CORRAL
Permit Finaled 11/29/2021 ERNESTO CORRAL

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/12/2020 PATRICK MISCHLICH
Address approval Cleared 6/23/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 6/23/2020 EMIL KYUPELYAN
Sewer availability Cleared 6/23/2020 EMIL KYUPELYAN
"D" conditions Cleared 8/19/2020 RUBEN VASQUEZ
"Q" conditions Cleared 8/19/2020 RUBEN VASQUEZ
Green Code Cleared 8/23/2020 JESSE ARELLANO

Contact Information

Contractor Yadgir Construction Inc; Lic. No.: 616203-B 230 E GLADSTONE STONE      SAN DIMAS, CA 91773

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/16/2020 Not Ready for Inspection LANNY MERRICK
Footing/Foundation/Slab 12/16/2020 Not Ready for Inspection LANNY MERRICK
Footing/Foundation/Slab 12/23/2020 Partial Approval NICK DANERI
Interior/Exterior Lathing 12/31/2020 Partial Approval LANNY MERRICK
Smoke Detectors 12/31/2020 Not Ready for Inspection LANNY MERRICK
Wood Frame 12/31/2020 Partial Approval LANNY MERRICK
Green Building Rough 1/15/2021 Not Ready for Inspection LANNY MERRICK
Wood Frame 1/15/2021 Partial Approval LANNY MERRICK
Drywall Nailing 1/27/2021 Partial Approval RONALD PACHECO
Interior/Exterior Lathing 2/26/2021 Partial Approval RONALD PACHECO
Final 4/12/2021 Not Ready for Inspection RONALD PACHECO
Green Building Final 4/12/2021 Not Ready for Inspection RONALD PACHECO
Green Building Rough 4/12/2021 Not Ready for Inspection RONALD PACHECO
SGSOV-Seismic Gas S/O Valve 4/12/2021 SGSOV Not Ready RONALD PACHECO
Smoke Detectors 4/12/2021 Not Ready for Inspection RONALD PACHECO
Wood Frame 4/12/2021 Not Ready for Inspection RONALD PACHECO
Final 6/11/2021 Not Ready for Inspection JONATHAN QUACH
Green Building Final 6/11/2021 Not Ready for Inspection JONATHAN QUACH
Green Building Rough 6/11/2021 Approved JONATHAN QUACH
SGSOV-Seismic Gas S/O Valve 6/11/2021 SGSOV Not Ready JONATHAN QUACH
Smoke Detectors 6/11/2021 Approved JONATHAN QUACH
Wood Frame 6/11/2021 Approved JONATHAN QUACH
Final 10/7/2021 Conditional Approval DANIEL COLLINS
Green Building Final 10/7/2021 Approved DANIEL COLLINS
SGSOV-Seismic Gas S/O Valve 10/7/2021 SGSOV Approved DANIEL COLLINS