1339 W 21ST ST 90732

Certificate Information: 1339 W 21ST ST 90732

Application / Permit
20016-10000-09930
Plan Check / Job No.
B20LA07239
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion existing detached recreation room into an ADU per state law GCS 65852.2(e)(1) (A). **COMPLY WITH DEPARTMENT ORDER effective date 02/28/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE.** 2 OF 2
Permit Issued
Issued on 3/23/2021
Issuing Office
Current Status
CofO Issued on 2/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/1/2020 APPLICANT
Assigned to Plan Check Engineer 5/22/2020 HELEN NGUYEN
Corrections Issued 5/26/2020 HELEN NGUYEN
Quality Review Completed 5/28/2020 STANLEY RAAP
Applicant returned to address corrections 8/4/2020 HELEN NGUYEN
Applicant returned to address corrections 8/10/2020 HELEN NGUYEN
Applicant returned to address corrections 8/25/2020 HELEN NGUYEN
Building Plans Picked Up 8/27/2020 APPLICANT
Plan Check Approved 3/18/2021 HELEN NGUYEN
Issued 3/23/2021 APPLICANT
CofO in Progress 12/21/2022 ANDREW BEELI
CofO in Progress 12/21/2022 ANDREW BEELI
CofO Issued 2/9/2023 BRUCE TODD
Permit Finaled 2/9/2023 BRUCE TODD

Permit Application Clearance Information

Address approval Cleared 9/2/2020 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 10/5/2020 ERIK BEASLEY
Sewer availability Cleared 10/5/2020 ERIK BEASLEY
Green Code Cleared 3/2/2021 HELEN NGUYEN

Contact Information

Contractor Owner-Builder       ,
Engineer Crook,, Barrett Cameron; Lic. No.: C57196 2036 CREEK RD      KITTY HAWK, NC 27949

Inspector Information

KELLY WARNER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
PAUL BECKER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
KEITH EDGHILL, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GONZALEZ, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/31/2021 Corrections Issued ANDREW BEELI
Special/Order Compliance 6/15/2021 Partial Inspection ANDREW BEELI
Footing/Foundation/Slab 6/29/2021 Not Ready for Inspection ANDREW BEELI
Footing/Foundation/Slab 7/14/2021 Approved ANDREW BEELI
PLUMBING-Rough 7/14/2021 Approved ANDREW BEELI
Floor/Roof Diaphrgm/Shear Wall 9/7/2021 Approved ANDREW BEELI
Interior/Exterior Lathing 9/7/2021 Approved ANDREW BEELI
Special/Order Compliance 9/30/2021 Approved ANDREW BEELI
ELECTRICAL-Rough 10/13/2021 Approved ANDREW BEELI
PLUMBING-Rough 10/13/2021 Approved ANDREW BEELI
Insulation 10/20/2021 Approved ANDREW BEELI
Drywall Nailing 11/9/2021 Approved ANDREW BEELI
Interior/Exterior Lathing 11/9/2021 Approved ANDREW BEELI
Shower Pan 11/9/2021 Partial Inspection ANDREW BEELI
PLUMBING-Rough 12/3/2021 Approved ANDREW BEELI
BUILDING-Rough-Frame 5/6/2022 Approved ANDREW BEELI
ELECTRICAL-Final 5/6/2022 Corrections Issued ANDREW BEELI
Final 5/6/2022 Corrections Issued ANDREW BEELI
HVAC-Final 5/6/2022 Partial Approval ANDREW BEELI
PLUMBING-Final 5/6/2022 Partial Approval ANDREW BEELI
SGSOV-Seismic Gas S/O Valve 5/6/2022 SGSOV Approved ANDREW BEELI
Smoke Detectors 5/6/2022 Approved ANDREW BEELI
Final 9/23/2022 Corrections Issued ANDREW BEELI
Final 12/21/2022 OK to Issue CofO ANDREW BEELI