1701 N GAFFEY ST 90731

Certificate Information: 1701 N GAFFEY ST 90731

Application / Permit
20016-10000-09908
Plan Check / Job No.
B20LA07223
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
INTERIOR TENANT IMPROVEMENT TO AN EXISTING TARGET SNACK BAR AREA. WORK TO INCLUDE: FIXTURE UPDATES, WALL, CEILING AND FLOOR FINISH UPDATES.
Permit Issued
Issued on 8/4/2020
Issuing Office
Current Status
Permit Finaled on 3/18/2026

Permit Application Status History

Submitted 4/21/2020 APPLICANT
Assigned to Plan Check Engineer 4/22/2020 SERGIO GUTIERREZ
Corrections Issued 5/4/2020 SERGIO GUTIERREZ
Applicant returned to address corrections 5/29/2020 GEORGE ALVAREZ
Plan Check Approved 5/29/2020 GEORGE ALVAREZ
Issued 8/4/2020 APPLICANT
Building Plans Picked Up 8/6/2020 APPLICANT
Permit Finaled 3/18/2026 DAVID TSAU

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/7/2020 ERIK BEASLEY
Sewer availability Cleared 5/7/2020 ERIK BEASLEY

Contact Information

Architect , ; Lic. No.: C38207       ,
Contractor Fulcrum Construction Inc; Lic. No.: 832993-B 13450 MAXELLA AVE STE 225      MARINA DEL REY, CA 90292

Inspector Information

MICHAEL PETRUSKO, (310) 732-4552 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 8/11/2020 Conditional Approval JOEY BUCHANAN
Pre-Inspection 8/11/2020 Approved JOEY BUCHANAN
T-Bar Ceiling 8/20/2020 Approved JOEY BUCHANAN
Final 9/28/2020 Conditional Approval JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 9/28/2020 SGSOV Approved JOEY BUCHANAN
Smoke Detectors 9/28/2020 Approved JOEY BUCHANAN
Final 3/16/2026 Partial Inspection DAVID TSAU
Final 3/18/2026 Permit Finaled DAVID TSAU