834 W 131ST ST 90247
Certificate Information: 834 W 131ST ST 90247
- Application / Permit
- 20016-10000-09882
- Plan Check / Job No.
- B20LA07205
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) RECREATION ROOM TO ADU.
- Permit Issued
- Issued on 5/20/2021
- Issuing Office
- Current Status
- CofO Issued on 12/4/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2020 | FERNANDO FLORES |
| Corrections Issued | 4/22/2020 | FERNANDO FLORES |
| Applicant returned to address corrections | 4/30/2021 | RICARDO RAMIREZ |
| Building Plans Picked Up | 5/3/2021 | APPLICANT |
| Plan Check Approved | 5/13/2021 | FERNANDO FLORES |
| Issued | 5/20/2021 | APPLICANT |
| CofO in Progress | 10/27/2021 | EUGENE CASSIDY |
| Permit Finaled | 12/4/2021 | DEROLD HAUFF |
| CofO Issued | 12/4/2021 | DEROLD HAUFF |
| Permit Finaled | 12/4/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/5/2021 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 5/5/2021 | ERIK BEASLEY |
| Sewer availability | Cleared | 5/5/2021 | ERIK BEASLEY |
Contact Information
| Contractor | Anaya Bros Construction; Lic. No.: 730856-B | P O BOX 5963 EL MONTE, CA 91734 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/3/2021 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 7/16/2021 | Partial Inspection | JOHN KLARIN |
| Underground Mechanical | 7/16/2021 | Partial Approval | JOHN KLARIN |
| ELECTRICAL-Rough | 8/12/2021 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 8/12/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 8/12/2021 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 8/16/2021 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 8/16/2021 | Approved | EUGENE CASSIDY |
| Insulation | 8/16/2021 | Approved | EUGENE CASSIDY |
| METHANE-Rough | 8/16/2021 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 8/18/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 8/18/2021 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Final | 8/18/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Final | 8/18/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 8/18/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 8/18/2021 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 8/18/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 8/20/2021 | Approved | EUGENE CASSIDY |
| HVAC-Final | 8/20/2021 | Conditional Approval | EUGENE CASSIDY |
| PLUMBING-Final | 8/20/2021 | Approved | EUGENE CASSIDY |
| Final | 9/1/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 9/1/2021 | Approved | EUGENE CASSIDY |
| Final | 10/18/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| Final | 10/21/2021 | Corrections Issued | EUGENE CASSIDY |
| Final | 10/26/2021 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 10/26/2021 | Approved | EUGENE CASSIDY |