1553 N SCHRADER BLVD 90028
Certificate Information: 1553 N SCHRADER BLVD 90028
- Application / Permit
- 20016-10000-09872
- Plan Check / Job No.
- B20LA07192
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (4) Gymnasium
- Work Description
- Tenant improvement interior alterations to lobby and office for exercise room. in existing YMCA Relocate two all gender toilet rooms and drinking fountain pair.new rooftop equipment.
- Permit Issued
- Issued on 1/7/2021
- Issuing Office
- Current Status
- Issued on 1/7/2021
Permit Application Status History
| Submitted | 5/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/18/2020 | ARSALAN SHABESTARI |
| Corrections Issued | 7/9/2020 | ARSALAN SHABESTARI |
| Quality Review Completed | 7/30/2020 | PRANITA SHAH |
| Disabled Access Plans Picked Up | 7/31/2020 | APPLICANT |
| Building Plans Picked Up | 8/5/2020 | APPLICANT |
| Green Plans Picked Up | 11/4/2020 | APPLICANT |
| Plan Check Approved | 1/7/2021 | ARSALAN SHABESTARI |
| Issued | 1/7/2021 | APPLICANT |
Permit Application Clearance Information
| "D" conditions | Cleared | 8/11/2020 | RICHARD REASER |
| ZA Case | Cleared | 8/11/2020 | RICHARD REASER |
| City Hist. Cultural Monument | Cleared | 8/18/2020 | MICAELA TORRES-GIL |
| Historic Resource Verification | Cleared | 8/18/2020 | MICAELA TORRES-GIL |
| Historic monument | Cleared | 8/18/2020 | MICAELA TORRES-GIL |
| Redevelopment Project Area | Cleared | 8/18/2020 | MICAELA TORRES-GIL |
| Green Code | Cleared | 9/29/2020 | KHEDER ALRAZAA |
| DAS Clearance | Cleared | 10/22/2020 | ARSALAN SHABESTARI |
Contact Information
| Contractor | Paradise Construction & Contract Management Inc; Lic. No.: 869786-B | 21261 STEELE PEAK DR PERRIS, CA 92570 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 3/12/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Light Gage Steel Frame | 3/26/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Drywall Nailing | 4/12/2021 | Approved | RUSSELL BONVOULOIR |
| T-Bar Ceiling | 5/17/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Final | 6/15/2023 | Partial Inspection | RONALD JIMENEZ |
| Green Building Final | 6/15/2023 | Approved | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 6/15/2023 | SGSOV Not Ready | RONALD JIMENEZ |
| Smoke Detectors | 6/15/2023 | Approved | RONALD JIMENEZ |