1115 W 25TH ST 90007
Certificate Information: 1115 W 25TH ST 90007
- Application / Permit
- 20016-10000-09852
- Plan Check / Job No.
- B20LA07167
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- DEMOLITION OF EXISTING OFFICE & TOILET ROOMS. CONSTRUCTION OF NEW OFFICES, WORK AREA, BREAK AREA, CLASS ROOMS, REMOVAL OF NON-STRUCTURAL PARTITIONS AND ACCESSIBLE TOILET ROOMS. NEW EXTERIOR DOOR OPENING. (NO CHANGE OF USE OR PARKING).
- Permit Issued
- Issued on 7/13/2020
- Issuing Office
- Current Status
- Permit Finaled on 3/11/2022
Permit Application Status History
| Submitted | 4/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2020 | CRISTINA SALAZAR |
| Corrections Issued | 4/22/2020 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 6/1/2020 | CRISTINA SALAZAR |
| Plan Check Approved | 6/15/2020 | FARSHAD ALIMOHAMADI |
| Issued | 7/13/2020 | APPLICANT |
| Building Plans Picked Up | 7/23/2020 | APPLICANT |
| Permit Finaled | 3/8/2022 | RUSSELL BONVOULOIR |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 5/13/2020 | HELEN JADALI |
| Eng Process Fee Ord 176,300 | Cleared | 5/21/2020 | CELINA MORENO |
Contact Information
| Architect | Simon,, Matthew Evans; Lic. No.: C29326 | 3956 GUNDRY AVENUE LONG BEACH, CA 90807 |
| Contractor | Con - Am Inc; Lic. No.: 698311-B | 903 CALLE AMANECER STE 210 SAN CLEMENTE, CA 92673 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/30/2020 | Partial Approval | LANNY MERRICK |
| Footing/Foundation/Slab | 10/6/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Light Gage Steel Frame | 10/14/2020 | Conditional Approval | LEOPOLDO MENDOZA |
| Insulation | 10/16/2020 | Partial Inspection | LEOPOLDO MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Drywall Nailing | 10/21/2020 | Partial Approval | LANNY MERRICK |
| Insulation | 10/26/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Insulation | 11/2/2020 | Approved | LANNY MERRICK |
| Light Gage Steel Frame | 11/2/2020 | Partial Approval | LANNY MERRICK |
| Drywall Nailing | 11/4/2020 | Approved | LANNY MERRICK |
| T-Bar Ceiling | 12/15/2020 | Approved | LANNY MERRICK |
| Final | 1/4/2021 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Green Building Final | 1/4/2021 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 1/4/2021 | SGSOV Not Ready | LEOPOLDO MENDOZA |
| Smoke Detectors | 1/4/2021 | Approved | LEOPOLDO MENDOZA |
| Final | 3/19/2021 | Corrections Issued | LEOPOLDO MENDOZA |
| Green Building Final | 3/19/2021 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 3/19/2021 | SGSOV Approved | LEOPOLDO MENDOZA |
| Final | 3/8/2022 | Permit Finaled | RUSSELL BONVOULOIR |
| Green Building Final | 3/8/2022 | Approved | RUSSELL BONVOULOIR |