2021 S ARLINGTON AVE 90018

Certificate Information: 2021 S ARLINGTON AVE 90018

Application / Permit
20016-10000-09851
Plan Check / Job No.
B20LA07165
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY SEISMIC RETROFIT PER LABC CHAPTER-93: INSTALL (4) SPECIAL CANTILEVERED STEEL COLUMNS WITH GRADE BEAMS.
Permit Issued
Issued on 1/6/2021
Issuing Office
Current Status
CofC Issued on 6/11/2021

Permit Application Status History

Submitted 4/21/2020 APPLICANT
Assigned to Plan Check Engineer 5/14/2020 YOUNG KIM
Corrections Issued 5/27/2020 YOUNG KIM
Quality Review Completed 5/29/2020 HANS SANTIAGO
Applicant returned to address corrections 6/18/2020 YOUNG KIM
Applicant returned to address corrections 7/2/2020 YOUNG KIM
Applicant returned to address corrections 7/17/2020 YOUNG KIM
Plan Check Approved 8/11/2020 YOUNG KIM
Issued 1/6/2021 APPLICANT
OK for CofC 5/26/2021 DARRYL ARNOLD
CofC Issued 6/11/2021 ERNESTO CORRAL

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 6/2/2020 MAXFIELD VERMY
Tenant Habitability Plan Cleared 1/4/2021 PHILLIP MUNGUIA

Contact Information

Contractor S F T Construction Corp; Lic. No.: 1009086-B 322 6TH STREET UNIT 4      SAN FRANCISCO, CA 94103
Engineer Ni,, Zhang Yuan; Lic. No.: C68149 743 S SIERRA VISTA AVE C      ALHAMBRA, CA 91801

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/9/2021 Approved DARRYL ARNOLD
Wood Frame 2/17/2021 Conditional Approval DARRYL ARNOLD
Excavation/Setback/Form/Re-Bar 2/23/2021 Not Ready for Inspection DARRYL ARNOLD
Footing/Foundation/Slab 2/23/2021 Conditional Approval DARRYL ARNOLD
Wood Frame 2/23/2021 Not Ready for Inspection DARRYL ARNOLD
Deputy Drilled-In Anchors 2/24/2021 Conditional Approval DARRYL ARNOLD
Deputy Wood Construction 2/24/2021 Conditional Approval DARRYL ARNOLD
Interior/Exterior Lathing 3/2/2021 Approved DARRYL ARNOLD
Final 5/26/2021 OK for CofC DARRYL ARNOLD
METHANE-Final 5/26/2021 Approved DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 5/26/2021 SGSOV Approved DARRYL ARNOLD
Smoke Detectors 5/26/2021 Approved DARRYL ARNOLD