5120 1/2 W 12TH ST 90019

Certificate Information: 5120 1/2 W 12TH ST 90019

Application / Permit
20016-10000-09828
Plan Check / Job No.
B20LA07143
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) second story recreation room above detached garage to Accessory Dwelling Unit per LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 12/17/2020
Issuing Office
Current Status
CofO Issued on 9/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/23/2020 APPLICANT
Assigned to Plan Check Engineer 4/23/2020 ADAM HEGAZI
Corrections Issued 5/4/2020 ADAM HEGAZI
Applicant returned to address corrections 6/11/2020 SINA KHOSRAVI
Applicant returned to address corrections 8/4/2020 AUNG SOE
Applicant returned to address corrections 12/8/2020 LUKE GONZALES
Plan Check Approved 12/11/2020 LUKE GONZALES
Issued 12/17/2020 APPLICANT
Building Plans Picked Up 12/24/2020 APPLICANT
CofO in Progress 9/12/2024 JUSTIN HAWLEY
CofO Issued 9/19/2024 DEROLD HAUFF
Permit Finaled 9/19/2024 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 10/5/2020 CHRISTINA PARK
Address approval Cleared 10/22/2020 JUAN ASHTON
Eng Process Fee Ord 176,300 Cleared 11/5/2020 PAMELA TENEZA
Sewer availability Cleared 12/10/2020 CECILIO NAVARRO

Contact Information

Contractor Owner-Builder       ,
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/23/2020 Corrections Issued STUART CHAPMAN
BUILDING-Rough-Frame 2/8/2021 Approved STUART CHAPMAN
Final 2/8/2021 Corrections Issued STUART CHAPMAN
METHANE-Final 2/8/2021 Approved STUART CHAPMAN
METHANE-Rough 2/8/2021 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 2/8/2021 SGSOV Not Ready STUART CHAPMAN
Smoke Detectors 2/8/2021 Approved STUART CHAPMAN
Final 4/8/2021 Not Ready for Inspection STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 4/8/2021 SGSOV Not Ready STUART CHAPMAN
Final 4/29/2021 Conditional Approval STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 4/29/2021 SGSOV Approved STUART CHAPMAN
Final 5/17/2021 Corrections Issued STUART CHAPMAN
Final 9/12/2024 OK to Issue CofO JUSTIN HAWLEY
HVAC-Final 9/12/2024 Approved JUSTIN HAWLEY