4701-4703 N AQUEDUCT AVE 91436
Certificate Information: 4701-4703 N AQUEDUCT AVE 91436
- Application / Permit
- 20016-10000-09771
- Plan Check / Job No.
- B20LA07119
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert existing attached garage to ADU (360 SF). Bathroom remodelling on main house. (No Structural Impact, No added bldg footprint)
- Permit Issued
- Issued on 6/9/2020
- Issuing Office
- Current Status
- CofO Issued on 8/16/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/23/2020 | JOE VO |
| Corrections Issued | 4/30/2020 | JOE VO |
| Quality Review Completed | 5/5/2020 | PRANITA SHAH |
| Applicant returned to address corrections | 5/27/2020 | JOE VO |
| Plan Check Approved | 6/2/2020 | JOE VO |
| Issued | 6/9/2020 | APPLICANT |
| CofO in Progress | 8/16/2021 | DAVID SANDOVAL |
| Permit Finaled | 8/16/2021 | MICHAEL SMITH |
| CofO Issued | 8/16/2021 | MICHAEL SMITH |
| Permit Finaled | 8/16/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/8/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 5/8/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 5/8/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/14/2020 | Approved | SEAN WIRCH |
| Footing/Foundation/Slab | 8/3/2020 | Approved | RONALD COWAN |
| PLUMBING-Rough | 8/27/2020 | Partial Approval | RONALD COWAN |
| BUILDING-Rough-Frame | 9/25/2020 | Corrections Issued | RONALD COWAN |
| ELECTRICAL-Rough | 9/25/2020 | Approved | RONALD COWAN |
| Green Building Rough | 9/25/2020 | Corrections Issued | RONALD COWAN |
| HVAC-Rough | 9/25/2020 | Approved | RONALD COWAN |
| PLUMBING-Rough | 9/25/2020 | Approved | RONALD COWAN |
| BUILDING-Rough-Frame | 10/5/2020 | Approved | RONALD COWAN |
| Green Building Rough | 10/5/2020 | Approved | RONALD COWAN |
| Shower Pan | 10/28/2020 | Approved | RONALD COWAN |
| Drywall Nailing | 11/9/2020 | Approved | RONALD COWAN |
| Shower Pan | 11/9/2020 | Approved | RONALD COWAN |
| Final | 4/19/2021 | Corrections Issued | RONALD COWAN |
| Green Building Final | 4/19/2021 | Approved | RONALD COWAN |
| SGSOV-Seismic Gas S/O Valve | 4/19/2021 | SGSOV Not Ready | RONALD COWAN |
| Smoke Detectors | 4/19/2021 | Approved | RONALD COWAN |
| Final | 6/24/2021 | Corrections Issued | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 6/24/2021 | SGSOV Approved | VINCENT HANLEY |
| Final | 8/3/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Final | 8/6/2021 | Corrections Issued | DAVID SANDOVAL |
| Final | 8/16/2021 | OK to Issue CofO | DAVID SANDOVAL |
| Service/Power Release | 8/16/2021 | Approved | DAVID SANDOVAL |