826 W 23RD ST 90731

Certificate Information: 826 W 23RD ST 90731

Application / Permit
20016-10000-09697
Plan Check / Job No.
B20LA07065
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING GARAGE INTO AN ADU. PER GCS 65852.2 (E)(1)(A)
Permit Issued
Issued on 8/7/2020
Issuing Office
Metro
Current Status
CofO Issued on 1/29/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/18/2020 APPLICANT
Assigned to Plan Check Engineer 4/20/2020 FARSHAD ALIMOHAMADI
Corrections Issued 4/21/2020 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 6/5/2020 AUNG SOE
Applicant returned to address corrections 7/6/2020 CRISTINA SALAZAR
Applicant returned to address corrections 7/23/2020 ZAW HAN
Plan Check Approved 7/29/2020 ZAW HAN
Issued 8/7/2020 APPLICANT
Building Plans Picked Up 8/7/2020 APPLICANT
CofO in Progress 1/29/2021 ANSON MAGLASANG
Permit Finaled 1/29/2021 DEROLD HAUFF
CofO Issued 1/29/2021 DEROLD HAUFF
Permit Finaled 1/29/2021 DEROLD HAUFF

Permit Application Clearance Information

Miscellaneous Cleared 4/29/2020 DANIEL CORONADO
Grading Pre-Inspection Cleared 5/8/2020 PATRICK MISCHLICH
Address approval Cleared 5/18/2020 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 5/18/2020 ERIK BEASLEY
Sewer availability Cleared 5/18/2020 ERIK BEASLEY

Contact Information

Contractor Owner-Builder       ,
Engineer Fernandez,, Agapito B; Lic. No.: C56546 7400 E SLAUSON AVE STE S      COMMERCE, CA 90040

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 8/14/2020 Not Ready for Inspection JOHN KLARIN
Footing/Foundation/Slab 8/14/2020 Partial Inspection JOHN KLARIN
ELECTRICAL-Rough 8/21/2020 Partial Inspection JOHN KLARIN
Gas Test 8/21/2020 Corrections Issued JOHN KLARIN
Gas Test 8/26/2020 Partial Approval JOHN KLARIN
Footing/Foundation/Slab 8/31/2020 Partial Inspection JOHN KLARIN
ELECTRICAL-Rough 9/8/2020 Not Ready for Inspection JOHN KLARIN
Footing/Foundation/Slab 9/8/2020 Approved JOHN KLARIN
Underground Mechanical 9/8/2020 Approved JOHN KLARIN
BUILDING-Rough-Frame 9/25/2020 Not Ready for Inspection JOHN KLARIN
Rough-Elec/Plmb/HVAC 9/25/2020 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 10/2/2020 Not Ready for Inspection JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 10/2/2020 Not Ready for Inspection JOHN KLARIN
Insulation 10/2/2020 Approved JOHN KLARIN
Rough-Elec/Plmb/HVAC 10/2/2020 Approved JOHN KLARIN
BUILDING-Rough-Frame 10/5/2020 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 10/5/2020 Approved JOHN KLARIN
Interior/Exterior Lathing 10/5/2020 Approved JOHN KLARIN
Drywall Nailing 10/13/2020 Approved JOHN KLARIN
ELECTRICAL-Final 11/16/2020 Approved JOHN KLARIN
Final 11/16/2020 Corrections Issued JOHN KLARIN
HVAC-Final 11/16/2020 Approved JOHN KLARIN
PLUMBING-Final 11/16/2020 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 11/16/2020 SGSOV Approved JOHN KLARIN
Smoke Detectors 11/16/2020 Approved JOHN KLARIN
Final 12/8/2020 Conditional Approval JOHN KLARIN
Service/Power Release 1/7/2021 Partial Inspection JOHN KLARIN
Special/Order Compliance 1/11/2021 No Access for Inspection JOHN KLARIN
Service/Power Release 1/26/2021 Approved JOHN KLARIN