5938 W AIRDROME ST 90035

Certificate Information: 5938 W AIRDROME ST 90035

Application / Permit
20016-10000-09664
Plan Check / Job No.
B20LA07049
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLAN: CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER ORDINANCE. ALL WORK PER WOOD FRAME PRESCRIPTIVE PROVISIONS.
Permit Issued
Issued on 6/8/2020
Issuing Office
Current Status
CofO Issued on 8/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/16/2020 APPLICANT
Assigned to Plan Check Engineer 4/20/2020 KEVIN MORALES
Corrections Issued 4/23/2020 KEVIN MORALES
Quality Review Completed 5/5/2020 PRANITA SHAH
Plan Check Approved 6/3/2020 KEVIN MORALES
Issued 6/8/2020 APPLICANT
CofO in Progress 8/23/2022 JOSE AVILA
Permit Finaled 8/23/2022 DEROLD HAUFF
CofO Issued 8/23/2022 DEROLD HAUFF
Permit Finaled 8/23/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/19/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 5/19/2020 RENZ SORIANO
Sewer availability Cleared 5/19/2020 RENZ SORIANO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/24/2021 Approved STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 10/20/2021 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 10/20/2021 Corrections Issued JOSE AVILA
Excavation/Setback/Form/Re-Bar 10/25/2021 Approved JOSE AVILA
Footing/Foundation/Slab 10/25/2021 Approved JOSE AVILA
ELECTRICAL-Rough 12/7/2021 Corrections Issued JOSE AVILA
PLUMBING-Rough 12/7/2021 Corrections Issued JOSE AVILA
PLUMBING-Rough 12/14/2021 Corrections Issued JOSE AVILA
Rough-Elec/Plmb/HVAC 12/14/2021 Corrections Issued JOSE AVILA
Sewer 12/14/2021 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 12/20/2021 Approved JOSE AVILA
PLUMBING-Rough 12/20/2021 Approved JOSE AVILA
HVAC-Rough 12/22/2021 Approved JOSE AVILA
Wood Frame 12/22/2021 Corrections Issued JOSE AVILA
HVAC-Rough 12/23/2021 Approved JOSE AVILA
Wood Frame 12/23/2021 Not Ready for Inspection JOSE AVILA
BUILDING-Rough-Frame 12/30/2021 Corrections Issued JOSE AVILA
HVAC-Rough 12/30/2021 Approved JOSE AVILA
METHANE-Rough 12/30/2021 Approved JOSE AVILA
Wood Frame 1/3/2022 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 1/20/2022 Partial Approval JOSE AVILA
Wood Frame 1/20/2022 Partial Approval JOSE AVILA
Insulation 2/9/2022 Approved JOSE AVILA
Interior/Exterior Lathing 2/9/2022 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 2/15/2022 Approved JOSE AVILA
Wood Frame 2/15/2022 Approved JOSE AVILA
Insulation 2/24/2022 Approved JOSE AVILA
Interior/Exterior Lathing 2/24/2022 Approved JOSE AVILA
Drywall Nailing 3/8/2022 Approved JOSE AVILA
Shower Pan 3/8/2022 Approved JOSE AVILA
Final 7/11/2022 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 7/11/2022 SGSOV Approved JOSE AVILA
Smoke Detectors 7/11/2022 Corrections Issued JOSE AVILA
ELECTRICAL-Final 8/1/2022 Approved JOSE AVILA
Final 8/1/2022 Corrections Issued JOSE AVILA
HVAC-Final 8/1/2022 Corrections Issued JOSE AVILA
PLUMBING-Final 8/1/2022 Approved JOSE AVILA
Smoke Detectors 8/1/2022 Approved JOSE AVILA
Final 8/23/2022 OK to Issue CofO JOSE AVILA