6553 N FULTON AVE 91401
Certificate Information: 6553 N FULTON AVE 91401
- Application / Permit
- 20016-10000-09661
- Plan Check / Job No.
- B20LA07046
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- EPLAN 3567 - Soft-Story seismic retrofit per LABC Chapter 93: Soft Story Retrofit. Install (1) OMF and (1) SCCS
- Permit Issued
- Issued on 9/3/2020
- Issuing Office
- Current Status
- CofC Issued on 1/6/2021
Permit Application Status History
| Submitted | 4/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2020 | VARAND SARKISIAN |
| Corrections Issued | 5/8/2020 | VARAND SARKISIAN |
| Quality Review Completed | 5/13/2020 | SAI KHUM |
| Plan Check Approved | 7/7/2020 | VARAND SARKISIAN |
| Issued | 9/3/2020 | APPLICANT |
| OK for CofC | 1/6/2021 | MARK FERRARI |
| CofC Issued | 1/6/2021 | MARK FERRARI |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 8/20/2020 | MICHAEL SOTO |
Contact Information
| Contractor | Biayna Corp; Lic. No.: 998853-B | , |
| Engineer | Muradyan,, David; Lic. No.: NA6232 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/11/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 9/14/2020 | Partial Approval | JOE VELASQUEZ |
| Deputy Drilled-In Anchors | 10/5/2020 | Conditional Approval | JONATHAN QUACH |
| Excavation/Setback/Form/Re-Bar | 10/7/2020 | Approved | JONATHAN QUACH |
| Deputy Reinf. Concrete | 10/13/2020 | Conditional Approval | JONATHAN QUACH |
| Structural Steel Frame | 10/16/2020 | Approved | JONATHAN QUACH |
| Wood Frame | 10/16/2020 | Approved | JONATHAN QUACH |
| Interior/Exterior Lathing | 10/22/2020 | Approved | JONATHAN QUACH |
| Final | 11/30/2020 | Not Ready for Inspection | HAMID PISHEHVAR |
| SGSOV-Seismic Gas S/O Valve | 11/30/2020 | SGSOV Not Ready | HAMID PISHEHVAR |
| Smoke Detectors | 11/30/2020 | Not Ready for Inspection | HAMID PISHEHVAR |
| Final | 12/2/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 12/2/2020 | SGSOV Approved | JOE VELASQUEZ |
| Smoke Detectors | 12/2/2020 | Approved | JOE VELASQUEZ |
| Final | 1/6/2021 | OK for CofC | MARK FERRARI |