6509 S VAN NESS AVE 90047
Certificate Information: 6509 S VAN NESS AVE 90047
- Application / Permit
- 20016-10000-09651
- Plan Check / Job No.
- B20LA07038
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL PLYWOOD SHEAR WALL.
- Permit Issued
- Issued on 3/4/2021
- Issuing Office
- Current Status
- CofC Issued on 2/23/2022
Permit Application Status History
| Submitted | 4/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/14/2020 | MANUEL MONTUFAR |
| Corrections Issued | 5/19/2020 | MANUEL MONTUFAR |
| Quality Review Completed | 5/21/2020 | SAI KHUM |
| Applicant returned to address corrections | 9/15/2020 | MANUEL MONTUFAR |
| Plan Check Approved | 10/7/2020 | MANUEL MONTUFAR |
| Issued | 3/4/2021 | APPLICANT |
| OK for CofC | 7/1/2021 | DARRYL ARNOLD |
| CofC Issued | 2/23/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| Construction near power lines | Cleared | 9/21/2020 | WALTER RAMIREZ |
| Construction within easement | Cleared | 9/21/2020 | WALTER RAMIREZ |
| Tenant Habitability Plan | Cleared | 2/22/2021 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Zebra Construction Inc; Lic. No.: 1055609-B | 145 S FAIRFAX STE 200/300 LOS ANGELES, CA 90036 |
| Engineer | Bishoff,, Ryan William; Lic. No.: NA6250 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 3/26/2021 | Not Ready for Inspection | JOEY BUCHANAN |
| Pre-Inspection | 3/26/2021 | Corrections Issued | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 3/26/2021 | SGSOV No Gas | JOEY BUCHANAN |
| Smoke Detectors | 3/26/2021 | Not Ready for Inspection | JOEY BUCHANAN |
| Deputy Other (see comments) | 4/22/2021 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 4/28/2021 | Not Ready for Inspection | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 4/29/2021 | Approved | JOEY BUCHANAN |
| Deputy Wood Construction | 5/5/2021 | Approved | JOEY BUCHANAN |
| Wood Frame | 5/17/2021 | Approved | JOEY BUCHANAN |
| Interior/Exterior Lathing | 5/19/2021 | Approved | JOEY BUCHANAN |
| Final | 6/8/2021 | Not Ready for Inspection | JOEY BUCHANAN |
| Smoke Detectors | 6/8/2021 | Not Ready for Inspection | JOEY BUCHANAN |
| Final | 6/25/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| Smoke Detectors | 6/25/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| Final | 6/30/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| Smoke Detectors | 6/30/2021 | Corrections Issued | DARRYL ARNOLD |
| Final | 7/1/2021 | OK for CofC | DARRYL ARNOLD |
| Smoke Detectors | 7/2/2021 | Approved | DARRYL ARNOLD |