2600 1/2 S DELEVAN DR 90065

Certificate Information: 2600 1/2 S DELEVAN DR 90065

Application / Permit
20016-10000-09530
Plan Check / Job No.
B20LA06920
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EXISTING ATTACHED GARAGE TO ADU PER GCS 65852.2 E 1 A
Permit Issued
Issued on 5/22/2020
Issuing Office
Metro
Current Status
CofO Issued on 9/24/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/15/2020 APPLICANT
Assigned to Plan Check Engineer 4/20/2020 STARR CHEN
Corrections Issued 5/20/2020 STARR CHEN
Applicant returned to address corrections 5/20/2020 TSE MING HUANG
Plan Check Approved 5/22/2020 TSE MING HUANG
Issued 5/22/2020 LADBS
CofO in Progress 9/3/2020 ELMER BLAND
Permit Finaled 9/24/2020 DEROLD HAUFF
CofO Issued 9/24/2020 DEROLD HAUFF
Permit Finaled 9/24/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/29/2020 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 4/29/2020 CECILIO NAVARRO
Sewer availability Cleared 4/29/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 5/5/2020 CECILIO NAVARRO
Hydrant and Access approval Cleared 5/14/2020 KURT CORRAL
Grading Pre-Inspection Cleared 5/15/2020 PATRICK MISCHLICH

Contact Information

Contractor Owner-Builder       ,
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/27/2020 Approved CRAIG VAUGHAN
Insulation 6/8/2020 Not Ready for Inspection CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 6/8/2020 Not Ready for Inspection CRAIG VAUGHAN
Wood Frame 6/8/2020 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 6/11/2020 Approved CRAIG VAUGHAN
HVAC-Rough 6/11/2020 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 6/11/2020 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 6/18/2020 Approved CRAIG VAUGHAN
HVAC-Rough 6/18/2020 Approved CRAIG VAUGHAN
Insulation 6/18/2020 Approved CRAIG VAUGHAN
Drywall Nailing 6/23/2020 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 6/23/2020 Partial Approval CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 7/31/2020 Approved CRAIG VAUGHAN
Final 7/31/2020 Corrections Issued CRAIG VAUGHAN
Green Building Final 7/31/2020 Corrections Issued CRAIG VAUGHAN
Green Building Rough 7/31/2020 Approved CRAIG VAUGHAN
MERV13>=Final 7/31/2020 Approved CRAIG VAUGHAN
MERV13>=Rough 7/31/2020 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 7/31/2020 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 7/31/2020 Approved CRAIG VAUGHAN
Final 8/6/2020 Corrections Issued CRAIG VAUGHAN
Green Building Final 8/6/2020 Approved CRAIG VAUGHAN
Final 8/17/2020 Conditional Approval CRAIG VAUGHAN
Final 9/3/2020 OK to Issue CofO ELMER BLAND