3143 W LARGA AVE 90039
Certificate Information: 3143 W LARGA AVE 90039
- Application / Permit
- 20016-10000-09491
- Plan Check / Job No.
- B20LA06893
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) NON CONFORMING REAR UNIT WITH ATTACHED GARAGE TO A DETACHED ACCESSORY DWELLING UNIT PER ORDINANCE
- Permit Issued
- Issued on 10/13/2020
- Issuing Office
- Current Status
- CofO Issued on 12/24/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/17/2020 | FERNANDO FLORES |
| Corrections Issued | 4/20/2020 | FERNANDO FLORES |
| Applicant returned to address corrections | 5/19/2020 | AMIR DANAI |
| Applicant returned to address corrections | 6/19/2020 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 7/13/2020 | AMIR DANAI |
| Plan Check Approved | 10/9/2020 | STANLEY RAAP |
| Issued | 10/13/2020 | APPLICANT |
| Building Plans Picked Up | 10/21/2020 | APPLICANT |
| CofO in Progress | 12/17/2020 | HAMIK HARTOUNIAN |
| Permit Finaled | 12/24/2020 | DEROLD HAUFF |
| CofO Issued | 12/24/2020 | DEROLD HAUFF |
| Permit Finaled | 12/24/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/12/2020 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2020 | RENZ SORIANO |
| Low Impact Development | Cleared | 7/29/2020 | JORGE MEJIA LEMUS |
| Sewer availability | Cleared | 8/11/2020 | PAMELA TENEZA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/27/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 10/27/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 11/4/2020 | Approved | HAMIK HARTOUNIAN |
| Insulation | 11/13/2020 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 11/16/2020 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 11/16/2020 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 11/16/2020 | Approved | HAMIK HARTOUNIAN |
| Final | 11/25/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 11/25/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Smoke Detectors | 11/25/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 12/15/2020 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Green Building Final | 12/15/2020 | Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 12/15/2020 | Approved | HAMIK HARTOUNIAN |