7800 N HASKELL AVE 91406
Certificate Information: 7800 N HASKELL AVE 91406
- Application / Permit
- 20016-10000-09395
- Plan Check / Job No.
- B20LA06822
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- ePlan TI. Change of use a portion of (E) warehouse to wholesale sales area and new offices.
- Permit Issued
- Issued on 6/17/2020
- Issuing Office
- Current Status
- CofO Issued on 3/19/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/15/2020 | HELEN NGUYEN |
| Corrections Issued | 4/16/2020 | HELEN NGUYEN |
| Applicant returned to address corrections | 5/26/2020 | VU NGUYEN |
| Applicant returned to address corrections | 5/27/2020 | VU NGUYEN |
| Applicant returned to address corrections | 6/2/2020 | KEVIN MORALES |
| Plan Check Approved | 6/9/2020 | KEVIN MORALES |
| Issued | 6/17/2020 | APPLICANT |
| CofO in Progress | 3/9/2021 | JEFFREY FULTON |
| Permit Finaled | 3/19/2021 | JEFFREY DURAN |
| CofO Issued | 3/19/2021 | JEFFREY DURAN |
| Permit Finaled | 3/19/2021 | JEFFREY DURAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/15/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 6/3/2020 | GUILLERMO PETRA |
Contact Information
| Architect | Sturgill,, Ben Curtis; Lic. No.: C23174 | 314 E BROADWAY # E GLENDALE, CA 91205 |
| Contractor | Preston Greg A; Lic. No.: 304202-B | P O BOX 871 NORTH HOLLYWOOD, CA 91603 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 10/27/2020 | Partial Inspection | JEFFREY FULTON |
| Insulation | 11/12/2020 | Approved | JEFFREY FULTON |
| Drywall Nailing | 11/18/2020 | Approved | JEFFREY FULTON |
| Drywall Nailing | 11/19/2020 | Not Ready for Inspection | DANNY RODRIGUEZ |
| T-Bar Ceiling | 12/22/2020 | Partial Inspection | JEFFREY FULTON |
| Final | 2/18/2021 | Not Ready for Inspection | JEFFREY FULTON |
| Reinforced Masonry Frame | 2/18/2021 | Approved | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 2/18/2021 | SGSOV Not Ready | JEFFREY FULTON |
| Smoke Detectors | 2/18/2021 | Approved | JEFFREY FULTON |
| Final | 3/4/2021 | OK to Issue CofO | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 3/4/2021 | SGSOV Approved | JEFFREY FULTON |