6135 N RESEDA BLVD 91335

Certificate Information: 6135 N RESEDA BLVD 91335

Application / Permit
20016-10000-09381
Plan Check / Job No.
B20LA06804
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT AS PER LABC CH. 93. INSTALL (2) OMF.
Permit Issued
Issued on 7/27/2020
Issuing Office
Current Status
CofC Issued on 12/11/2020

Permit Application Status History

Submitted 4/17/2020 APPLICANT
Assigned to Plan Check Engineer 5/6/2020 JESSE VIDUYA
Corrections Issued 5/14/2020 JESSE VIDUYA
Quality Review Completed 5/19/2020 SAI KHUM
Building Plans Picked Up 5/20/2020 APPLICANT
Applicant returned to address corrections 6/15/2020 JESSE VIDUYA
Plan Check Approved 7/8/2020 JESSE VIDUYA
Issued 7/27/2020 APPLICANT
OK for CofC 12/11/2020 ERNESTO CORRAL
CofC Issued 12/11/2020 ERNESTO CORRAL

Permit Application Clearance Information

Tenant Habitability Plan Cleared 7/22/2020 PHILLIP MUNGUIA

Contact Information

Contractor Core Contractors Llc; Lic. No.: 1038618-B 9800D TOPANGA CANYON BLVD   SUITE 324    CHATSWORTH, CA 91311
Engineer Deihimi,, Amir Hossein; Lic. No.: C78194 23172 PLAZA POINTE DR STE 145      LAGUNA HILLS, CA 92653

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 9/21/2020 No Access for Inspection DANIEL VARNUM
Pre-Inspection 9/21/2020 Partial Inspection DANIEL VARNUM
Deputy Drilled-In Anchors 9/22/2020 Conditional Approval DANIEL VARNUM
Interior/Exterior Lathing 9/23/2020 Approved DANIEL VARNUM
Deputy Steel/Welding 9/25/2020 Conditional Approval DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 9/28/2020 Conditional Approval DANIEL VARNUM
Footing/Foundation/Slab 9/28/2020 Conditional Approval DANIEL VARNUM
Structural Steel Frame 9/28/2020 Not Ready for Inspection DANIEL VARNUM
Deputy Steel/Welding 9/29/2020 Conditional Approval DANIEL VARNUM
Final 10/2/2020 Not Ready for Inspection DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 10/2/2020 SGSOV Not Ready DANIEL VARNUM
Smoke Detectors 10/2/2020 Not Ready for Inspection DANIEL VARNUM
Final 10/6/2020 Partial Inspection DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 10/6/2020 SGSOV Approved DANIEL VARNUM
Smoke Detectors 10/6/2020 Approved DANIEL VARNUM
Final 12/11/2020 OK for CofC ERNESTO CORRAL