714 W LOOKOUT DR 90012

Certificate Information: 714 W LOOKOUT DR 90012

Application / Permit
20016-10000-09369
Plan Check / Job No.
B20LA06792
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT PER LABC CHAPTER 93 USING 1 SMF
Permit Issued
Issued on 2/8/2023
Issuing Office
Metro
Current Status
CofC Issued on 6/28/2023

Permit Application Status History

Submitted 4/13/2020 APPLICANT
Assigned to Plan Check Engineer 5/6/2020 AUNG SOE
Corrections Issued 5/18/2020 AUNG SOE
Quality Review Completed 5/21/2020 SAI KHUM
Building Plans Picked Up 5/22/2020 APPLICANT
Applicant returned to address corrections 9/10/2020 AUNG SOE
Plan Check Approved 9/11/2020 AUNG SOE
Issued 2/8/2023 APPLICANT
OK for CofC 6/28/2023 DARRYL ARNOLD
CofC Issued 6/28/2023 WINSTON DUNNING

Permit Application Clearance Information

Abandoned oil well Cleared 7/14/2020 KURT CORRAL
Abandoned oil well approval Cleared 7/14/2020 KURT CORRAL
Tenant Habitability Plan Cleared 2/6/2023 RICARDO BOHORQUEZ

Contact Information

Contractor Zebra Construction Inc; Lic. No.: 1055609-B 2523 S ROBERTSON BLVD      LOS ANGELES, CA 90034
Engineer Tajvidi,, Seyed Mohammad; Lic. No.: C84559 9163 LEROY STREET      SAN GABRIEL, CA 91775

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/24/2023 Corrections Issued VAHE KELEDJIAN
Deputy Drilled-In Anchors 4/26/2023 Conditional Approval VAHE KELEDJIAN
Footing/Foundation/Slab 4/28/2023 Corrections Issued VAHE KELEDJIAN
Structural Steel Frame 4/28/2023 Partial Inspection VAHE KELEDJIAN
Wood Frame 4/28/2023 Approved VAHE KELEDJIAN
Footing/Foundation/Slab 5/1/2023 Conditional Approval DARRYL ARNOLD
Structural Steel Frame 5/1/2023 Corrections Issued DARRYL ARNOLD
Wood Frame 5/1/2023 Conditional Approval DARRYL ARNOLD
Wood Frame 5/11/2023 Approved VAHE KELEDJIAN
Drywall Nailing 5/22/2023 Approved VAHE KELEDJIAN
Final 6/9/2023 Partial Approval JULIAN CAPUCETTI
METHANE-Final 6/9/2023 Approved JULIAN CAPUCETTI
SGSOV-Seismic Gas S/O Valve 6/9/2023 SGSOV Approved JULIAN CAPUCETTI
Smoke Detectors 6/9/2023 Approved JULIAN CAPUCETTI
Final 6/28/2023 OK for CofC DARRYL ARNOLD