6930 N FULTON AVE 91605

Certificate Information: 6930 N FULTON AVE 91605

Application / Permit
20016-10000-09295
Plan Check / Job No.
B20LA06724
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT AS PER LABC CHAPTER 93. INSTALL TWO (N) specail cantilever columns
Permit Issued
Issued on 9/1/2020
Issuing Office
Current Status
CofC Issued on 1/21/2021

Permit Application Status History

Submitted 4/21/2020 APPLICANT
Assigned to Plan Check Engineer 5/14/2020 JESSE VIDUYA
Corrections Issued 5/21/2020 JESSE VIDUYA
Quality Review Completed 5/21/2020 HANS SANTIAGO
Building Plans Picked Up 5/26/2020 APPLICANT
Plan Check Approved 6/16/2020 JESSE VIDUYA
Issued 9/1/2020 APPLICANT
OK for CofC 1/6/2021 JOE VELASQUEZ
CofC Issued 1/21/2021 RICKEY JACKSON

Permit Application Clearance Information

Tenant Habitability Plan Cleared 8/24/2020 MICHAEL SOTO

Contact Information

Contractor Alpha Structural Inc; Lic. No.: 663409-B 8334 FOOTHILL BLVD      SUNLAND, CA 91040
Engineer Demers,, Joe Alan; Lic. No.: C71535 1626 S MAYFLOWER AVE UNIT B      MONROVIA, CA 91016

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/14/2020 Not Ready for Inspection JOE VELASQUEZ
Deputy Drilled-In Anchors 9/23/2020 No Access for Inspection JOE VELASQUEZ
Deputy Steel/Welding 9/23/2020 No Access for Inspection JOE VELASQUEZ
Excavation/Setback/Form/Re-Bar 9/23/2020 Corrections Issued JOE VELASQUEZ
Structural Steel Frame 9/23/2020 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 9/23/2020 Not Ready for Inspection JOE VELASQUEZ
Footing/Foundation/Slab 9/24/2020 Not Ready for Inspection JOE VELASQUEZ
Excavation/Setback/Form/Re-Bar 9/25/2020 Approved JOE VELASQUEZ
Wood Frame 9/25/2020 Not Ready for Inspection JOE VELASQUEZ
Structural Steel Frame 9/29/2020 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 9/29/2020 Not Ready for Inspection JOE VELASQUEZ
Insulation 10/1/2020 Approved JOE VELASQUEZ
Interior/Exterior Lathing 12/17/2020 Approved JOE VELASQUEZ
Final 1/6/2021 OK for CofC JOE VELASQUEZ
SGSOV-Seismic Gas S/O Valve 1/6/2021 SGSOV Approved JOE VELASQUEZ
Smoke Detectors 1/6/2021 Approved JOE VELASQUEZ