424 N LARCHMONT BLVD 90004
Certificate Information: 424 N LARCHMONT BLVD 90004
- Application / Permit
- 20016-10000-09290
- Plan Check / Job No.
- B20LA06718
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 19 SF addition to (E) 2 story type V SFD /Accessory Artwork exhibition studio , interior TI, alternation to entry, new exterior 17'HX7'W steel swing window, and exterior site improvement (No Use Change).
- Permit Issued
- Issued on 7/14/2020
- Issuing Office
- Current Status
- CofO Issued on 7/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/23/2020 | SUEN LIEU |
| Disabled Access Plans Picked Up | 4/29/2020 | APPLICANT |
| Corrections Issued | 5/4/2020 | SUEN LIEU |
| Quality Review Completed | 5/7/2020 | CHARLES CHANG |
| Building Plans Picked Up | 5/12/2020 | APPLICANT |
| Applicant returned to address corrections | 5/29/2020 | SUEN LIEU |
| Applicant returned to address corrections | 6/4/2020 | SUEN LIEU |
| Applicant returned to address corrections | 6/10/2020 | SUEN LIEU |
| Applicant returned to address corrections | 6/16/2020 | SUEN LIEU |
| Applicant returned to address corrections | 6/18/2020 | SUEN LIEU |
| Applicant returned to address corrections | 6/23/2020 | SUEN LIEU |
| Applicant returned to address corrections | 6/29/2020 | SUEN LIEU |
| Plan Check Approved | 7/9/2020 | SUEN LIEU |
| Issued | 7/14/2020 | APPLICANT |
| CofO in Progress | 6/9/2021 | CHRIS CHRISTENSEN |
| Permit Finaled | 7/2/2021 | DEROLD HAUFF |
| CofO Issued | 7/2/2021 | DEROLD HAUFF |
| Permit Finaled | 7/2/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| "Q" conditions | Cleared | 7/9/2020 | ANACANY HURTADO |
| DAS Clearance | Cleared | 7/9/2020 | EDDIE GARIN |
Contact Information
| Architect | Lockyer,, Robert Sean; Lic. No.: C34804 | 457 N PALM CANYON DRIVE SUITE B PALM SPRINGS, CA 92262 |
| Contractor | Sean Lockyer Architects Inc; Lic. No.: 981751-B | 457 N PALM CANYON DRIVE SUITE B PALM SPRINGS, CA 92262 |
| Engineer | Martin,, Tod David; Lic. No.: S4096 | 547 E 6TH AVE ESCONDIDO, CA 92025 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/16/2020 | Approved | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 7/16/2020 | Off-Hour Fees Due | |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 7/16/2020 | Approved | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 7/16/2020 | Off-Hour Fees Due | |
| METHANE-Barrier | 7/16/2020 | Approved | CHRIS CHRISTENSEN |
| METHANE-Barrier | 7/16/2020 | Off-Hour Fees Due | |
| METHANE-Subgrade | 7/16/2020 | Approved | CHRIS CHRISTENSEN |
| METHANE-Subgrade | 7/16/2020 | Off-Hour Fees Due | |
| Pre-Inspection | 7/16/2020 | Approved | CHRIS CHRISTENSEN |
| Pre-Inspection | 7/16/2020 | Off-Hour Fees Due | |
| Underground Mechanical | 7/16/2020 | Approved | CHRIS CHRISTENSEN |
| Deputy Drilled-In Anchors | 7/22/2020 | Conditional Approval | THOMAS LOGRASSO |
| Deputy Reinf. Concrete | 7/22/2020 | Conditional Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 7/24/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 7/24/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Grounding or Bonding | 7/24/2020 | Approved | CHRIS CHRISTENSEN |
| Insulation | 7/24/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| METHANE-Rough | 7/24/2020 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 7/24/2020 | SGSOV Approved | CHRIS CHRISTENSEN |
| Structural Steel Frame | 7/24/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Wood Frame | 7/24/2020 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 9/11/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 9/11/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Gas Test | 9/11/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 9/11/2020 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Rough | 9/11/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 9/11/2020 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 9/11/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 10/20/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Rough-Elec/Plmb/HVAC | 10/20/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Smoke Detectors | 10/20/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 10/26/2020 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Wood Frame | 10/26/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 11/2/2020 | No Access for Inspection | ELMER BLAND |
| BUILDING-Rough-Frame | 11/18/2020 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 11/18/2020 | Approved | CHRIS CHRISTENSEN |
| Insulation | 11/18/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 11/18/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Rough-Elec/Plmb/HVAC | 11/18/2020 | Approved | CHRIS CHRISTENSEN |
| Green Building Final | 11/23/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Rough | 11/23/2020 | Approved | CHRIS CHRISTENSEN |
| Insulation | 11/23/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 11/23/2020 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 11/30/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Insulation | 11/30/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Drywall Nailing | 1/7/2021 | Approved | CHRIS CHRISTENSEN |
| Insulation | 1/7/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Final | 2/11/2021 | Not Ready for Inspection | ROBERT VORHIS |
| HVAC-Final | 2/11/2021 | Not Ready for Inspection | ROBERT VORHIS |
| HVAC-Final | 2/25/2021 | Partial Inspection | CHRIS CHRISTENSEN |
| HVAC-Final | 4/1/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Final | 5/20/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Final | 5/20/2021 | Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 5/20/2021 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 5/27/2021 | Approved | CHRIS CHRISTENSEN |
| Gas Test | 5/27/2021 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 5/27/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| PLUMBING-Final | 5/27/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 6/1/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Service/Power Release | 6/3/2021 | Not Required | CHRIS CHRISTENSEN |
| Final | 6/9/2021 | OK to Issue CofO | CHRIS CHRISTENSEN |
| HVAC-Final | 6/9/2021 | Approved | CHRIS CHRISTENSEN |