1030 1/2 W 55TH ST 90037
Certificate Information: 1030 1/2 W 55TH ST 90037
- Application / Permit
- 20016-10000-09289
- Plan Check / Job No.
- B20LA06716
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT GARAGE TO ADU PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 5/20/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/30/2020 | CRYSTEL MAALOUF |
| Corrections Issued | 5/5/2020 | CRYSTEL MAALOUF |
| Green Plans Picked Up | 5/7/2020 | APPLICANT |
| Quality Review Completed | 5/18/2020 | BILL STUTSMAN |
| Building Plans Picked Up | 5/19/2020 | APPLICANT |
| Applicant returned to address corrections | 1/21/2022 | CRYSTEL MAALOUF |
| Plan Check Approved | 5/13/2022 | CRYSTEL MAALOUF |
| Issued | 5/20/2022 | APPLICANT |
| CofO in Progress | 6/12/2024 | CRAIG DAVIS |
| CofO in Progress | 6/12/2024 | CRAIG DAVIS |
| Permit Finaled | 7/29/2024 | DEROLD HAUFF |
| CofO Issued | 7/29/2024 | DEROLD HAUFF |
| Permit Finaled | 7/29/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/20/2021 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 7/20/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 7/20/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2021 | CECILIO NAVARRO |
| Green Code | Cleared | 5/11/2022 | DONALD CRICHLOW |
Contact Information
| Architect | Wilkins,, Karen; Lic. No.: C27930 | 785 QUINTANA ROAD #180 MORRO BAY, CA 93442 |
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/7/2023 | Conditional Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 7/10/2023 | Corrections Issued | SABAS ALONSO |
| BUILDING-Rough-Frame | 8/15/2023 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 8/15/2023 | Approved | SABAS ALONSO |
| Green Building Rough | 8/15/2023 | Approved | SABAS ALONSO |
| HVAC-Rough | 8/15/2023 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 8/15/2023 | Partial Approval | SABAS ALONSO |
| PLUMBING-Rough | 8/15/2023 | Approved | SABAS ALONSO |
| Service/Power Release | 8/15/2023 | Not Ready for Inspection | SABAS ALONSO |
| Sewer | 8/15/2023 | Not Ready for Inspection | SABAS ALONSO |
| Insulation | 8/21/2023 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 9/12/2023 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 9/12/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 10/19/2023 | Approved | RONNIE MINDANAO |
| Final | 5/13/2024 | Corrections Issued | CRAIG DAVIS |
| Green Building Final | 5/13/2024 | Corrections Issued | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 5/13/2024 | SGSOV Approved | CRAIG DAVIS |
| Smoke Detectors | 5/13/2024 | Approved | CRAIG DAVIS |
| Final | 6/7/2024 | Partial Inspection | CRAIG DAVIS |
| Green Building Final | 6/7/2024 | Approved | CRAIG DAVIS |
| ELECTRICAL-Final | 6/11/2024 | Approved | CRAIG DAVIS |
| Final | 6/11/2024 | OK to Issue CofO | CRAIG DAVIS |
| HVAC-Final | 6/11/2024 | Approved | CRAIG DAVIS |
| PLUMBING-Final | 6/11/2024 | Approved | CRAIG DAVIS |
| Service/Power Release | 6/11/2024 | Approved | CRAIG DAVIS |