2424 1/2-3/4 E 4TH ST 90033

Certificate Information: 2424 1/2-3/4 E 4TH ST 90033

Application / Permit
20016-10000-09261
Plan Check / Job No.
B20LA06687
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
ADD NEW UNIT TO AN (E) DUPLEX. CHANGE OF USE FROM A DUPLEX TO AN APARTMENT. Per Section 1011 of LAEBC and Section 903.2.8 of LABC, an automatic sprinkler system shall be provided throughout all buildings.
Permit Issued
Issued on 12/1/2020
Issuing Office
Current Status
Issued on 12/1/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/10/2020 APPLICANT
Assigned to Plan Check Engineer 4/30/2020 CHUNG-WEN CHUANG
Corrections Issued 5/8/2020 CHUNG-WEN CHUANG
Green Plans Picked Up 5/15/2020 APPLICANT
Quality Review Completed 5/21/2020 KESETE HAREGOT
Applicant returned to address corrections 11/19/2020 CHUNG-WEN CHUANG
Plan Check Approved 11/20/2020 CHUNG-WEN CHUANG
Issued 12/1/2020 APPLICANT

Permit Application Clearance Information

Green Code Cleared 5/13/2020 DONALD CRICHLOW
Address approval Cleared 8/11/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 8/11/2020 THOMAS LANG
Sewer availability Cleared 8/11/2020 THOMAS LANG
Clean Up Green Up Cleared 8/12/2020 ANACANY HURTADO
ZI Cleared 8/12/2020 ANACANY HURTADO
Historic Resource Verification Cleared 8/14/2020 MICAELA TORRES-GIL
Redevelopment Project Area Cleared 9/23/2020 DAVID URITA
ZI Cleared 9/23/2020 DAVID URITA
Tenant Habitability Plan Cleared 10/14/2020 PHILLIP MUNGUIA
DAS Clearance Cleared 11/20/2020 CHUNG-WEN CHUANG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Final 4/6/2021 Not Ready for Inspection RONALD PACHECO
Green Building Final 4/6/2021 Not Ready for Inspection RONALD PACHECO
METHANE-Final 4/6/2021 Not Ready for Inspection RONALD PACHECO
Final 10/27/2022 Corrections Issued MARK FERRARI
Green Building Final 10/27/2022 Not Ready for Inspection MARK FERRARI
METHANE-Final 10/27/2022 Not Ready for Inspection MARK FERRARI
Final 2/21/2023 Not Ready for Inspection RAFAEL CORTES
Green Building Final 2/21/2023 Not Ready for Inspection RAFAEL CORTES
METHANE-Final 2/21/2023 Approved RAFAEL CORTES
Pre-Inspection 5/13/2024 Corrections Issued RONALD JIMENEZ
Green Building Rough 9/16/2024 Approved RONALD JIMENEZ
Wood Frame 9/16/2024 Approved RONALD JIMENEZ
Pre-Inspection 3/5/2025 Corrections Issued RONALD JIMENEZ