1234 S WESTCHESTER PL 90019
Certificate Information: 1234 S WESTCHESTER PL 90019
- Application / Permit
- 20016-10000-09220
- Plan Check / Job No.
- B20LA06651
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT PORTION OF EXISTING ACCESSORY STRUCTURE (LIVING QUARTERS) TO NEW ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 9/3/2020
- Issuing Office
- Current Status
- CofO Issued on 8/31/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2020 | MANUEL MONTUFAR |
| Corrections Issued | 4/23/2020 | MANUEL MONTUFAR |
| Quality Review Completed | 5/5/2020 | TU HUA |
| Applicant returned to address corrections | 7/13/2020 | MANUEL MONTUFAR |
| Applicant returned to address corrections | 7/16/2020 | MANUEL MONTUFAR |
| Plan Check Approved | 9/3/2020 | MANUEL MONTUFAR |
| Issued | 9/3/2020 | APPLICANT |
| CofO in Progress | 3/31/2022 | GLEN RAND |
| Permit Finaled | 8/31/2022 | BRUCE TODD |
| CofO Issued | 8/31/2022 | BRUCE TODD |
Permit Application Clearance Information
| Address approval | Cleared | 6/12/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 6/12/2020 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 6/15/2020 | RENZ SORIANO |
| HPOZ | Cleared | 6/17/2020 | AMANDA KAINER |
| Construction near power lines | Cleared | 8/27/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/27/2020 | RIDWAN HARDY |
Contact Information
| Architect | Kim,, Jane H; Lic. No.: C31396 | 1161 CRENSHAW BLVD. LOS ANGELES, CA 90019 |
Inspector Information
| LUIS CORRAL, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| DONALD WONG, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM DOEPPING, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM MICHALAK, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/16/2020 | Corrections Issued | GLEN RAND |
| ELECTRICAL-Rough | 3/4/2021 | Corrections Issued | GLEN RAND |
| ELECTRICAL-Final | 3/19/2021 | Corrections Issued | GLEN RAND |
| PLUMBING-Rough | 5/26/2021 | Approved | GLEN RAND |
| Sewer | 5/26/2021 | Approved | GLEN RAND |
| ELECTRICAL-Rough | 9/24/2021 | Corrections Issued | GLEN RAND |
| Interior/Exterior Lathing | 9/24/2021 | Partial Approval | GLEN RAND |
| Drywall Nailing | 10/14/2021 | Approved | GLEN RAND |
| ELECTRICAL-Final | 10/14/2021 | Approved | GLEN RAND |
| ELECTRICAL-Rough | 10/14/2021 | Approved | GLEN RAND |
| Shower Pan | 10/14/2021 | Approved | GLEN RAND |
| SGSOV-Seismic Gas S/O Valve | 11/29/2021 | SGSOV Not Ready | GLEN RAND |
| PLUMBING-Final | 3/22/2022 | Not Ready for Inspection | WILLIAM MICHALAK |
| PLUMBING-Final | 3/29/2022 | Approved | GLEN RAND |
| BUILDING-Rough-Frame | 3/31/2022 | Approved | GLEN RAND |
| Final | 3/31/2022 | OK to Issue CofO | GLEN RAND |
| METHANE-Final | 3/31/2022 | Approved | GLEN RAND |
| METHANE-Rough | 3/31/2022 | Approved | GLEN RAND |
| SGSOV-Seismic Gas S/O Valve | 3/31/2022 | SGSOV Approved | GLEN RAND |
| Smoke Detectors | 3/31/2022 | Approved | GLEN RAND |