1729 W 64TH ST 90047
Certificate Information: 1729 W 64TH ST 90047
- Application / Permit
- 20016-10000-09181
- Plan Check / Job No.
- B20LA06606
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION AND CONVERSION OF (E) GARAGE TO ADU PER GCS 65852.2(e) (1)(A).
- Permit Issued
- Issued on 1/25/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/17/2020 | LUKE GONZALES |
| Corrections Issued | 5/4/2020 | LUKE GONZALES |
| Applicant returned to address corrections | 6/1/2020 | TSE MING HUANG |
| Applicant returned to address corrections | 1/27/2021 | SHANGQIN XIE |
| Applicant returned to address corrections | 4/23/2021 | FARSHAD ALIMOHAMADI |
| Building Plans Picked Up | 6/18/2021 | APPLICANT |
| Applicant returned to address corrections | 12/13/2022 | STANLEY RAAP |
| Plan Check Approved | 1/25/2023 | CRISTINA SALAZAR |
| Issued | 1/25/2023 | APPLICANT |
| CofO in Progress | 8/30/2024 | CRAIG DAVIS |
| CofO Issued | 9/17/2024 | DEROLD HAUFF |
| Permit Finaled | 9/17/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| ZI | Cleared | 6/5/2020 | KENTON TRINH |
| Hydrant and Access approval | Cleared | 6/17/2020 | MATTHEW CRAIG |
| Address approval | Cleared | 11/13/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 11/19/2021 | THAN WIN |
| Sewer availability | Cleared | 11/19/2021 | THAN WIN |
| Low Impact Development | Cleared | 12/13/2022 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 12/13/2022 | TREVOR QUAN |
| Tenant Habitability Plan | Cleared | 12/13/2022 | JUAN ACOSTA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/17/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Underground Mechanical | 8/17/2023 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 8/23/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 11/28/2023 | Corrections Issued | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2023 | Approved | CRAIG DAVIS |
| ELECTRICAL-Rough | 1/10/2024 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 1/10/2024 | Approved | ENRIQUE MIRELES |
| Insulation | 1/12/2024 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 1/22/2024 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 1/22/2024 | Not Ready for Inspection | JOSE MACIAS |
| Drywall Nailing | 1/25/2024 | No Access for Inspection | RONNIE MINDANAO |
| Interior/Exterior Lathing | 1/25/2024 | No Access for Inspection | RONNIE MINDANAO |
| Drywall Nailing | 1/29/2024 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 1/29/2024 | Approved | JOSE MACIAS |
| Gas Test | 4/1/2024 | Corrections Issued | CRAIG DAVIS |
| BUILDING-Rough-Frame | 7/1/2024 | Corrections Issued | CRAIG DAVIS |
| Final | 7/1/2024 | Corrections Issued | CRAIG DAVIS |
| Green Building Final | 7/1/2024 | Corrections Issued | CRAIG DAVIS |
| Green Building Rough | 7/1/2024 | Approved | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 7/1/2024 | SGSOV Not Ready | CRAIG DAVIS |
| Smoke Detectors | 7/1/2024 | Approved | CRAIG DAVIS |
| BUILDING-Rough-Frame | 8/6/2024 | Corrections Issued | MICHAEL LEWIS |
| Final | 8/6/2024 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 8/6/2024 | Corrections Issued | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 8/6/2024 | SGSOV Not Ready | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 8/12/2024 | Partial Approval | CRAIG DAVIS |
| Final | 8/12/2024 | Corrections Issued | CRAIG DAVIS |
| Green Building Final | 8/12/2024 | Corrections Issued | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 8/12/2024 | SGSOV Not Ready | CRAIG DAVIS |
| Special/Order Compliance | 8/15/2024 | Not Ready for Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 8/21/2024 | Partial Approval | CRAIG DAVIS |
| Final | 8/21/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Green Building Final | 8/21/2024 | Corrections Issued | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 8/21/2024 | SGSOV Not Ready | CRAIG DAVIS |
| BUILDING-Rough-Frame | 8/26/2024 | Approved | CRAIG DAVIS |
| ELECTRICAL-Final | 8/26/2024 | Partial Approval | CRAIG DAVIS |
| Final | 8/26/2024 | Partial Approval | CRAIG DAVIS |
| Green Building Final | 8/26/2024 | Approved | CRAIG DAVIS |
| HVAC-Final | 8/26/2024 | Approved | CRAIG DAVIS |
| PLUMBING-Final | 8/26/2024 | Approved | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 8/26/2024 | SGSOV Approved | CRAIG DAVIS |
| Service/Power Release | 8/28/2024 | Approved | CRAIG DAVIS |
| ELECTRICAL-Final | 8/29/2024 | Approved | CRAIG DAVIS |
| Final | 8/29/2024 | OK to Issue CofO | CRAIG DAVIS |
| HVAC-Final | 8/29/2024 | Approved | CRAIG DAVIS |
| PLUMBING-Final | 8/29/2024 | Approved | CRAIG DAVIS |