4071 E RIGALI AVE 90039
Certificate Information: 4071 E RIGALI AVE 90039
- Application / Permit
- 20016-10000-09172
- Plan Check / Job No.
- B20LA06598
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN. CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A).
- Permit Issued
- Issued on 8/13/2020
- Issuing Office
- Current Status
- CofO Issued on 5/20/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/30/2020 | KEVIN MORALES |
| Corrections Issued | 5/6/2020 | KEVIN MORALES |
| Quality Review Completed | 5/14/2020 | PRANITA SHAH |
| Plan Check Approved | 7/28/2020 | KEVIN MORALES |
| Issued | 8/13/2020 | APPLICANT |
| CofO in Progress | 5/18/2021 | HAMIK HARTOUNIAN |
| Permit Finaled | 5/20/2021 | DEROLD HAUFF |
| CofO Issued | 5/20/2021 | DEROLD HAUFF |
| Permit Finaled | 5/20/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/26/2020 | CELINA MORENO |
| Sewer availability | Cleared | 6/26/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 6/29/2020 | CELINA MORENO |
| ZI | Cleared | 7/10/2020 | MAXFIELD VERMY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/17/2020 | Approved | HAMIK HARTOUNIAN |
| Pre-Inspection | 9/30/2020 | Approved | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 11/18/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 11/20/2020 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 2/18/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 2/18/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 2/18/2021 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 3/11/2021 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2021 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 3/22/2021 | Approved | HAMIK HARTOUNIAN |
| Insulation | 3/22/2021 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 3/22/2021 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 3/31/2021 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 3/31/2021 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 3/31/2021 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 5/7/2021 | Approved | HAMIK HARTOUNIAN |
| Final | 5/7/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Gas Test | 5/7/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 5/7/2021 | Approved | HAMIK HARTOUNIAN |
| HVAC-Final | 5/7/2021 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Final | 5/7/2021 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 5/7/2021 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 5/7/2021 | Approved | HAMIK HARTOUNIAN |
| Final | 5/17/2021 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Gas Test | 5/17/2021 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Final | 5/17/2021 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 5/17/2021 | SGSOV Approved | HAMIK HARTOUNIAN |