3783 S CHERRYWOOD AVE 90018
Certificate Information: 3783 S CHERRYWOOD AVE 90018
- Application / Permit
- 20016-10000-09146
- Plan Check / Job No.
- B20LA06568
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER STATE LAW GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 8/11/2020
- Issuing Office
- Current Status
- CofO Issued on 1/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/23/2020 | MICHAEL LOPEZ |
| Corrections Issued | 4/30/2020 | MICHAEL LOPEZ |
| Quality Review Completed | 6/2/2020 | QUAN NGHIEM |
| Green Plans Picked Up | 7/15/2020 | APPLICANT |
| Applicant returned to address corrections | 7/22/2020 | MICHAEL LOPEZ |
| Plan Check Approved | 7/23/2020 | MICHAEL LOPEZ |
| Building Plans Picked Up | 7/23/2020 | APPLICANT |
| Issued | 8/11/2020 | APPLICANT |
| CofO in Progress | 1/12/2021 | DAVID FEILER |
| Permit Finaled | 1/15/2021 | DEROLD HAUFF |
| CofO Issued | 1/15/2021 | DEROLD HAUFF |
| Permit Finaled | 1/15/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/9/2020 | ELAINE LEI |
| Sewer availability | Cleared | 6/9/2020 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 6/12/2020 | ELAINE LEI |
| Green Code | Cleared | 7/14/2020 | MICHAEL LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hamilton,, John O; Lic. No.: C53284 | P O BOX 866 HAWTHORNE, CA 90251 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/28/2020 | Corrections Issued | COREY HUPP |
| Footing/Foundation/Slab | 9/3/2020 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 9/10/2020 | Corrections Issued | COREY HUPP |
| ELECTRICAL-Rough | 9/10/2020 | Not Ready for Inspection | COREY HUPP |
| Green Building Rough | 9/10/2020 | Not Ready for Inspection | COREY HUPP |
| BUILDING-Rough-Frame | 9/22/2020 | Not Ready for Inspection | DAVID FEILER |
| Green Building Rough | 9/22/2020 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 9/30/2020 | Approved | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2020 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 9/30/2020 | Approved | DAVID FEILER |
| Wood Frame | 9/30/2020 | Partial Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2020 | Not Ready for Inspection | DAVID FEILER |
| Insulation | 10/23/2020 | Not Ready for Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 11/17/2020 | Approved | DAVID FEILER |
| Green Building Rough | 11/17/2020 | Approved | DAVID FEILER |
| Insulation | 11/17/2020 | Approved | DAVID FEILER |
| Wood Frame | 11/17/2020 | Approved | DAVID FEILER |
| Drywall Nailing | 11/23/2020 | Approved | DAVID FEILER |
| Shower Pan | 11/23/2020 | Approved | DAVID FEILER |
| Final | 12/3/2020 | Not Ready for Inspection | STUART CHAPMAN |
| Green Building Final | 12/3/2020 | Not Ready for Inspection | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 12/3/2020 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 12/3/2020 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 12/8/2020 | Partial Inspection | DAVID FEILER |
| Final | 12/24/2020 | OK to Issue CofO | DAVID FEILER |
| Green Building Final | 12/24/2020 | Approved | DAVID FEILER |
| Service/Power Release | 12/24/2020 | Approved | DAVID FEILER |
| Smoke Detectors | 12/24/2020 | Approved | DAVID FEILER |