741 E BROOKS AVE 90291

Certificate Information: 741 E BROOKS AVE 90291

Application / Permit
20016-10000-09144
Plan Check / Job No.
B20LA06566
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE STAIRCASE AND STAIR ACCESS TO THE ROOF ON THE 3RD FLOOR OF (E) SFD WITH A NEW SCREEN WALL FOR ROOF MOUNTED AC UNITS (SEE COMMENTS)
Permit Issued
Issued on 1/15/2021
Issuing Office
Current Status
Permit Closed on 8/21/2024

Permit Application Status History

Submitted 4/9/2020 APPLICANT
Assigned to Plan Check Engineer 4/9/2020 FARSHAD ALIMOHAMADI
Corrections Issued 4/21/2020 FARSHAD ALIMOHAMADI
Quality Review Completed 6/5/2020 STANLEY RAAP
Building Plans Picked Up 6/9/2020 APPLICANT
Applicant returned to address corrections 1/6/2021 FARSHAD ALIMOHAMADI
Plan Check Approved 1/11/2021 FARSHAD ALIMOHAMADI
Issued 1/15/2021 APPLICANT
Intent to Revoke-Status Void 8/27/2021 BINH PHAN
Re-Activate Permit 5/16/2023 CHARMIE HUYNH
Permit Closed-Status Void 8/24/2023 HERBERT GIRON
Permit Closed 8/24/2023 HERBERT GIRON
Re-Activate Permit 8/21/2024 HERBERT GIRON

Permit Application Clearance Information

Miscellaneous Cleared 6/9/2020 TERRI OSBORNE
Miscellaneous Cleared 6/9/2020 TERRI OSBORNE
Low Impact Development Cleared 6/25/2020 ORVAL HERNANDEZ-MARCI
ZA Case Cleared 7/20/2020 TERRI OSBORNE
Coastal Zone Cleared 9/3/2020 TERRI OSBORNE
Eng Process Fee Ord 176,300 Cleared 9/9/2020 DINAH GARIN
Roof/Waste drainage to street Cleared 9/30/2020 DINAH GARIN
Specific Plan Cleared 10/15/2020 KEVIN FULTON

Contact Information

Contractor True Building Inc; Lic. No.: 938015-B 1064 MYRA AVE      LOS ANGELES, CA 90029
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364
Engineer Vondra,, Thomas Edwin; Lic. No.: L8761 4717 W AVE M-8      QUARTZ HILL, CA 93536

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 3/3/2021 Approved JOHNNY MIRANDA
Wood Frame 3/3/2021 Partial Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 3/19/2021 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 3/19/2021 Partial Approval JOHNNY MIRANDA
Green Building Rough 3/19/2021 Not Ready for Inspection JOHNNY MIRANDA
ELECTRICAL-Rough 3/31/2021 Conditional Approval JOHNNY MIRANDA
Drywall Nailing 4/12/2021 Approved JOHNNY MIRANDA
Insulation 5/28/2021 Approved JUAN VALENZUELA
Interior/Exterior Lathing 5/28/2021 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 8/24/2023 Approved HERBERT GIRON
Final 8/24/2023 Permit Closed HERBERT GIRON
Footing/Foundation/Slab 8/24/2023 Approved HERBERT GIRON
Green Building Final 8/24/2023 Approved HERBERT GIRON
Green Building Rough 8/24/2023 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 8/24/2023 SGSOV Approved HERBERT GIRON
Smoke Detectors 8/24/2023 Approved HERBERT GIRON