3018 S FIGUEROA ST 90007
Certificate Information: 3018 S FIGUEROA ST 90007
- Application / Permit
- 20016-10000-09043
- Plan Check / Job No.
- B20LA06511
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- ePlan TI. for a Temporary Leasing Office. No change in parking
- Permit Issued
- Issued on 6/24/2020
- Issuing Office
- Current Status
- Permit Finaled on 9/11/2020
Permit Application Status History
| Submitted | 4/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/15/2020 | MONICA RAMIREZ |
| Corrections Issued | 4/15/2020 | MONICA RAMIREZ |
| Applicant returned to address corrections | 4/29/2020 | MONICA RAMIREZ |
| Plan Check Approved | 5/6/2020 | MONICA RAMIREZ |
| Issued | 6/24/2020 | APPLICANT |
| Permit Finaled | 9/9/2020 | LANNY MERRICK |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 4/29/2020 | MICAELA TORRES-GIL |
| Miscellaneous | Cleared | 4/29/2020 | ANNA VIDAL |
| Redevelopment Project Area | Cleared | 4/29/2020 | DAVID URITA |
Contact Information
| Architect | Antunovich,, Joseph Michael; Lic. No.: C8708 | 224 W HURON ST 7TH FL CHICAGO, IL 606543981 |
| Contractor | Weinbaum Construction; Lic. No.: 1048505-B | 1465 ELIN POINTE DR EL SEGUNDO, CA 90245 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 7/16/2020 | Not Ready for Inspection | LANNY MERRICK |
| Light Gage Steel Frame | 7/20/2020 | Partial Approval | LANNY MERRICK |
| Drywall Nailing | 7/23/2020 | Partial Approval | LANNY MERRICK |
| Drywall Nailing | 7/27/2020 | Not Ready for Inspection | LANNY MERRICK |
| Drywall Nailing | 7/29/2020 | Approved | LANNY MERRICK |
| Final | 8/19/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 8/19/2020 | SGSOV No Gas | LEOPOLDO MENDOZA |
| Smoke Detectors | 8/19/2020 | Approved | LEOPOLDO MENDOZA |
| Final | 9/2/2020 | Not Ready for Inspection | LANNY MERRICK |
| Final | 9/9/2020 | Permit Finaled | LANNY MERRICK |