- CONVERT 1-STORY DETACHED GARAGE TO ADU. ADU conversion of (E) 360sf garage to be a studio w/ kitchen and bath. NFPA 13-D sprinklers to be installed in lieu of the 150' requirement.
- Permit Issued
- Issued on 9/10/2020
- Issuing Office
- Current Status
- CofO Issued on 7/23/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/17/2020 | JESSE JIMENEZ |
| Corrections Issued | 4/20/2020 | JESSE JIMENEZ |
| Applicant returned to address corrections | 5/18/2020 | AMIR DANAI |
| Applicant returned to address corrections | 6/8/2020 | FERNANDO FLORES |
| Applicant returned to address corrections | 7/15/2020 | AUNG SOE |
| Plan Check Approved | 7/21/2020 | AUNG SOE |
| Issued | 9/10/2020 | APPLICANT |
| Building Plans Picked Up | 9/11/2020 | APPLICANT |
| CofO in Progress | 7/20/2022 | SABAS ALONSO |
| Permit Finaled | 7/23/2022 | DEROLD HAUFF |
| CofO Issued | 7/23/2022 | DEROLD HAUFF |
| Permit Finaled | 7/23/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/27/2020 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 5/27/2020 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/28/2020 | EMIL KYUPELYAN |
| Hydrant and Access approval | Cleared | 6/22/2020 | KURT CORRAL |
Contact Information
| Architect | Spierer,, Joseph Robert; Lic. No.: C32307 | 707 TORRANCE BLVD SUITE 100 REDONDO BEACH, CA 90277 |
| Contractor | 3d Contractors Inc; Lic. No.: 1017030-B | 6559 FERGUSON DRIVE COMMERCE, CA 90022 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/16/2020 | No Access for Inspection | ELMER BLAND |
| Footing/Foundation/Slab | 9/18/2020 | Approved | FREDDIE RIVERA |
| Pre-Inspection | 9/18/2020 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 10/6/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 10/7/2020 | Partial Approval | DAVID FEILER |
| Footing/Foundation/Slab | 10/9/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 10/14/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Wood Frame | 11/17/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| MERV13>=Rough | 12/4/2020 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Wood Frame | 12/4/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 1/5/2021 | Approved | ALEJANDRO DE ARTOLA |
| Wood Frame | 1/5/2021 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Insulation | 1/6/2021 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 1/11/2021 | Approved | ALEJANDRO DE ARTOLA |
| Final | 1/29/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Final | 1/29/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| MERV13>=Final | 1/29/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| MERV13>=Rough | 1/29/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 1/29/2021 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 1/29/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Wood Frame | 1/29/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 10/20/2021 | No Access for Inspection | SABAS ALONSO |
| Green Building Final | 10/20/2021 | No Access for Inspection | SABAS ALONSO |
| MERV13>=Final | 10/20/2021 | No Access for Inspection | SABAS ALONSO |
| MERV13>=Rough | 10/20/2021 | No Access for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 10/20/2021 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 10/20/2021 | No Access for Inspection | SABAS ALONSO |
| Wood Frame | 10/20/2021 | No Access for Inspection | SABAS ALONSO |
| Final | 11/1/2021 | Conditional Approval | HORACE FULTZ |
| Green Building Final | 11/1/2021 | Approved | HORACE FULTZ |
| MERV13>=Final | 11/1/2021 | Approved | HORACE FULTZ |
| MERV13>=Rough | 11/1/2021 | Approved | HORACE FULTZ |
| SGSOV-Seismic Gas S/O Valve | 11/1/2021 | SGSOV Not Required | HORACE FULTZ |
| Smoke Detectors | 11/1/2021 | Approved | HORACE FULTZ |
| Wood Frame | 11/1/2021 | Approved | HORACE FULTZ |
| Final | 12/13/2021 | Corrections Issued | SABAS ALONSO |
| Final | 12/21/2021 | Partial Inspection | ADAM ESCOTO |
| Final | 3/7/2022 | Conditional Approval | HORACE FULTZ |
| Final | 7/19/2022 | OK to Issue CofO | SABAS ALONSO |