CONVERT 1-STORY DETACHED GARAGE TO ADU. ADU conversion of (E) 360sf garage to be a studio w/ kitchen and bath. NFPA 13-D sprinklers to be installed in lieu of the 150' requirement.
Permit Issued
Issued on 9/10/2020
Issuing Office
Current Status
CofO Issued on 7/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/16/2020 APPLICANT
Assigned to Plan Check Engineer 4/17/2020 JESSE JIMENEZ
Corrections Issued 4/20/2020 JESSE JIMENEZ
Applicant returned to address corrections 5/18/2020 AMIR DANAI
Applicant returned to address corrections 6/8/2020 FERNANDO FLORES
Applicant returned to address corrections 7/15/2020 AUNG SOE
Plan Check Approved 7/21/2020 AUNG SOE
Issued 9/10/2020 APPLICANT
Building Plans Picked Up 9/11/2020 APPLICANT
CofO in Progress 7/20/2022 SABAS ALONSO
Permit Finaled 7/23/2022 DEROLD HAUFF
CofO Issued 7/23/2022 DEROLD HAUFF
Permit Finaled 7/23/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/27/2020 EMIL KYUPELYAN
Sewer availability Cleared 5/27/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 5/28/2020 EMIL KYUPELYAN
Hydrant and Access approval Cleared 6/22/2020 KURT CORRAL

Contact Information

Architect Spierer,, Joseph Robert; Lic. No.: C32307 707 TORRANCE BLVD SUITE 100      REDONDO BEACH, CA 90277
Contractor 3d Contractors Inc; Lic. No.: 1017030-B 6559 FERGUSON DRIVE      COMMERCE, CA 90022
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/16/2020 No Access for Inspection ELMER BLAND
Footing/Foundation/Slab 9/18/2020 Approved FREDDIE RIVERA
Pre-Inspection 9/18/2020 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 10/6/2020 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 10/7/2020 Partial Approval DAVID FEILER
Footing/Foundation/Slab 10/9/2020 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 10/14/2020 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/17/2020 Corrections Issued ALEJANDRO DE ARTOLA
Wood Frame 11/17/2020 Corrections Issued ALEJANDRO DE ARTOLA
MERV13>=Rough 12/4/2020 Not Ready for Inspection ALEJANDRO DE ARTOLA
Wood Frame 12/4/2020 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 1/5/2021 Approved ALEJANDRO DE ARTOLA
Wood Frame 1/5/2021 Conditional Approval ALEJANDRO DE ARTOLA
Insulation 1/6/2021 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 1/11/2021 Approved ALEJANDRO DE ARTOLA
Final 1/29/2021 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 1/29/2021 Not Ready for Inspection EUGENE CASSIDY
MERV13>=Final 1/29/2021 Not Ready for Inspection EUGENE CASSIDY
MERV13>=Rough 1/29/2021 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 1/29/2021 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 1/29/2021 Not Ready for Inspection EUGENE CASSIDY
Wood Frame 1/29/2021 Not Ready for Inspection EUGENE CASSIDY
Final 10/20/2021 No Access for Inspection SABAS ALONSO
Green Building Final 10/20/2021 No Access for Inspection SABAS ALONSO
MERV13>=Final 10/20/2021 No Access for Inspection SABAS ALONSO
MERV13>=Rough 10/20/2021 No Access for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 10/20/2021 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 10/20/2021 No Access for Inspection SABAS ALONSO
Wood Frame 10/20/2021 No Access for Inspection SABAS ALONSO
Final 11/1/2021 Conditional Approval HORACE FULTZ
Green Building Final 11/1/2021 Approved HORACE FULTZ
MERV13>=Final 11/1/2021 Approved HORACE FULTZ
MERV13>=Rough 11/1/2021 Approved HORACE FULTZ
SGSOV-Seismic Gas S/O Valve 11/1/2021 SGSOV Not Required HORACE FULTZ
Smoke Detectors 11/1/2021 Approved HORACE FULTZ
Wood Frame 11/1/2021 Approved HORACE FULTZ
Final 12/13/2021 Corrections Issued SABAS ALONSO
Final 12/21/2021 Partial Inspection ADAM ESCOTO
Final 3/7/2022 Conditional Approval HORACE FULTZ
Final 7/19/2022 OK to Issue CofO SABAS ALONSO