6840 N DE SOTO AVE 91303

Certificate Information: 6840 N DE SOTO AVE 91303

Application / Permit
20016-10000-08990
Plan Check / Job No.
B20LA06473
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Ice Cream Parlor
Work Description
Change of use from Retail to Ice Cream Parlor.
Permit Issued
Issued on 7/29/2020
Issuing Office
Current Status
CofO Issued on 9/10/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/10/2020 APPLICANT
Assigned to Plan Check Engineer 4/13/2020 SALVADOR QUINTANILLA
Corrections Issued 4/13/2020 SALVADOR QUINTANILLA
Applicant returned to address corrections 5/27/2020 SALVADOR QUINTANILLA
Plan Check Approved 6/22/2020 SALVADOR QUINTANILLA
Issued 7/29/2020 APPLICANT
Building Plans Picked Up 8/25/2020 APPLICANT
CofO in Progress 8/30/2021 JEFFREY FULTON
Permit Finaled 9/10/2021 JEFFREY DURAN
CofO Issued 9/10/2021 JEFFREY DURAN
Permit Finaled 9/10/2021 JEFFREY DURAN

Permit Application Clearance Information

ZA Case Cleared 4/20/2020 TERRI OSBORNE
ZA Case Cleared 4/20/2020 TERRI OSBORNE
ZA Case Cleared 4/20/2020 TERRI OSBORNE
ZA Case Cleared 4/20/2020 TERRI OSBORNE
ZA Case Cleared 4/20/2020 TERRI OSBORNE
ZA Case Cleared 4/20/2020 TERRI OSBORNE
ZA Case Cleared 4/20/2020 TERRI OSBORNE
Sewer availability Cleared 4/21/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/22/2020 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 4/22/2020 LEE GUILBEAUX
Public Works-Sewers Cleared 4/22/2020 LEE GUILBEAUX
Food Service Establishment Cleared 5/20/2020 JASH PATEL
Comm Cor/Mini-Mall Cleared 5/27/2020 ANACANY HURTADO
Food establishment approval Cleared 5/28/2020 LACDHS APPROVED
Specific Plan Cleared 6/18/2020 KRISTINE JEGALIAN

Contact Information

Contractor Ventmart Hoods Master; Lic. No.: 1020158-B 1800 E GARRY AVE STE #109      SANTA ANA, CA 92705
Engineer Wu,, Harold Ping-Hung; Lic. No.: C35693 1168 SAN GABRIEL BLVD NO N      ROSEMEAD, CA 91770

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/21/2020 Not Ready for Inspection DANIEL VARNUM
Wood Frame 9/18/2020 Corrections Issued JEFFREY FULTON
Light Gage Steel Frame 9/24/2020 Not Ready for Inspection DANIEL VARNUM
Light Gage Steel Frame 10/2/2020 No Access for Inspection JEFFREY FULTON
Light Gage Steel Frame 10/6/2020 Corrections Issued DANIEL VARNUM
Light Gage Steel Frame 10/14/2020 Partial Inspection PAUL DAVIDSON
Light Gage Steel Frame 12/30/2020 Corrections Issued JEFFREY FULTON
Light Gage Steel Frame 1/8/2021 Not Ready for Inspection DANIEL VARNUM
Drywall Nailing 1/14/2021 Partial Approval DANIEL VARNUM
Drywall Nailing 3/23/2021 Approved CAMERON CHABAN
T-Bar Ceiling 3/23/2021 Corrections Issued CAMERON CHABAN
Final 5/24/2021 Not Ready for Inspection CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 5/24/2021 SGSOV Not Ready CAMERON CHABAN
Smoke Detectors 5/24/2021 Not Ready for Inspection CAMERON CHABAN
Final 6/23/2021 Partial Inspection CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 6/23/2021 SGSOV Not Ready CAMERON CHABAN
Smoke Detectors 6/23/2021 Approved CAMERON CHABAN
Final 6/26/2021 Partial Inspection CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 6/26/2021 SGSOV No Gas CAMERON CHABAN
Final 7/22/2021 OK to Issue CofO JEFFREY FULTON