8900 W VENICE BLVD LEVEL 2 90232
Certificate Information: 8900 W VENICE BLVD LEVEL 2 90232
- Application / Permit
- 20016-10000-08977
- Plan Check / Job No.
- B20LA06461
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- ATTN: ADAM H. TENANT IMPROVEMENT ON LEVEL 2 OF AN EXISTING COMMERCIAL OFFICE BUILDING (TYPE 1B). SCOPE INCLUDES CONSTRUCTION OF NEW NON-LOAD BEARING PARTITIONS, MILLWORK, DOORS & FRAMES, CARPET, PAINT, FIXTURES & FURNITURE SYSTEMS.
- Permit Issued
- Issued on 5/12/2020
- Issuing Office
- Current Status
- Issued on 5/12/2020
Permit Application Status History
| Submitted | 4/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2020 | ADAM HEGAZI |
| Corrections Issued | 4/14/2020 | ADAM HEGAZI |
| Plan Check Approved | 4/22/2020 | ADAM HEGAZI |
| Issued | 5/12/2020 | APPLICANT |
| Building Plans Picked Up | 5/12/2020 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Herst,, Hans Robert; Lic. No.: C12001 | 500 S FIGUEROA AVENUE LOS ANGELES, CA 90071 |
| Contractor | G C X Llc; Lic. No.: 1045286-B | 29209 LARO DRIVE AGOURA HILLS, CA 91301 |
| Contractor | Owner-Builder | , |
| Engineer | Chang,, Wayne Chia-Wei; Lic. No.: S4751 | 19210 S VERMONT AVE BLDG B STE 210 GARDENA, CA 90248 |
Inspector Information
| PAUL DAVIDSON, (310) 914-3914 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 7/30/2020 | Partial Inspection | SORIN CIRSTOIU |
| Light Gage Steel Frame | 7/31/2020 | Partial Approval | JEFF BYTHEWAY |
| Drywall Nailing | 8/10/2020 | Partial Approval | JEFF BYTHEWAY |
| Reinforced Concrete Frame | 10/22/2020 | Approved | SORIN CIRSTOIU |
| Light Gage Steel Frame | 2/23/2021 | Partial Approval | JEFF BYTHEWAY |
| Light Gage Steel Frame | 4/14/2021 | Partial Approval | JEFF BYTHEWAY |
| Light Gage Steel Frame | 5/12/2021 | Partial Approval | JEFF BYTHEWAY |
| T-Bar Ceiling | 5/12/2021 | Approved | JEFF BYTHEWAY |
| Light Gage Steel Frame | 5/20/2021 | Approved | JEFF BYTHEWAY |
| Light Gage Steel Frame | 6/9/2021 | Partial Inspection | SORIN CIRSTOIU |
| Light Gage Steel Frame | 6/14/2021 | Partial Approval | JEFF BYTHEWAY |
| Final | 7/16/2021 | Not Ready for Inspection | JEFF BYTHEWAY |
| Green Building Final | 7/16/2021 | Not Ready for Inspection | JEFF BYTHEWAY |
| SGSOV-Seismic Gas S/O Valve | 7/16/2021 | SGSOV Approved | JEFF BYTHEWAY |
| Smoke Detectors | 7/16/2021 | Approved | JEFF BYTHEWAY |
| Final | 7/20/2021 | Not Ready for Inspection | JEFF BYTHEWAY |
| Green Building Final | 7/20/2021 | Not Ready for Inspection | JEFF BYTHEWAY |