1636 N HASLAM TER 90069

Certificate Information: 1636 N HASLAM TER 90069

Application / Permit
20016-10000-08974
Plan Check / Job No.
B20LA06451
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR AND EXTERIOR REMODEL TO EXISTING SFD W GARAGE
Permit Issued
Issued on 2/3/2021
Issuing Office
Current Status
Permit Finaled on 9/19/2024

Permit Application Status History

Submitted 4/7/2020 APPLICANT
Assigned to Plan Check Engineer 4/23/2020 STARR CHEN
Corrections Issued 5/1/2020 STARR CHEN
Quality Review Completed 5/4/2020 LAWRENCE QUIRANTE
Building Plans Picked Up 5/19/2020 APPLICANT
Green Plans Picked Up 6/18/2020 APPLICANT
Applicant returned to address corrections 11/16/2020 STARR CHEN
Applicant returned to address corrections 1/7/2021 STARR CHEN
Plan Check Approved 2/3/2021 STARR CHEN
Issued 2/3/2021 APPLICANT
Re-Activate Permit 3/22/2024 RAUL BARAJAS
Permit Expired-Status Void 3/22/2024 RAUL BARAJAS
Permit Finaled 9/18/2024 CRAIG VAUGHAN

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 5/20/2020 EMIL KYUPELYAN
BHO/Hillside ordinance Cleared 5/20/2020 EMIL KYUPELYAN
BHO/Hillside ordinance Cleared 5/20/2020 EMIL KYUPELYAN
Roof/Waste drainage to street Cleared 5/20/2020 EMIL KYUPELYAN
Sewer availability Cleared 5/20/2020 EMIL KYUPELYAN
Green Code Cleared 6/18/2020 STARR CHEN
Eng Process Fee Ord 176,300 Cleared 7/13/2020 EMIL KYUPELYAN
Hydrant and Access approval Cleared 9/2/2020 KURT CORRAL
Grading Pre-Inspection Cleared 10/15/2020 PATRICK MISCHLICH

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 5/26/2021 Corrections Issued BRAD BESCOS
Pre-Inspection 1/9/2023 Corrections Issued RAUL BARAJAS
Pre-Inspection 9/27/2023 Corrections Issued RAUL BARAJAS
Pre-Inspection 1/19/2024 Not Ready for Inspection RAUL BARAJAS
HVAC-Rough 4/9/2024 Corrections Issued RAUL BARAJAS
HVAC-Rough 4/15/2024 Approved RAUL BARAJAS
PLUMBING-Rough 4/15/2024 Corrections Issued RAUL BARAJAS
BUILDING-Rough-Frame 4/22/2024 Not Ready for Inspection ROY SPAULDING
PLUMBING-Rough 4/22/2024 Partial Approval ROY SPAULDING
BUILDING-Rough-Frame 5/2/2024 Corrections Issued RAUL BARAJAS
BUILDING-Rough-Frame 5/9/2024 Approved RAUL BARAJAS
Interior/Exterior Lathing 5/20/2024 Approved RAUL BARAJAS
Insulation 5/29/2024 Approved RAUL BARAJAS
Drywall Nailing 6/18/2024 Approved RAUL BARAJAS
Shower Pan 6/18/2024 Approved RAUL BARAJAS
PLUMBING-Final 8/16/2024 Partial Inspection RAUL BARAJAS
HVAC-Final 8/20/2024 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Final 8/26/2024 Not Ready for Inspection RAUL BARAJAS
Final 8/26/2024 Corrections Issued RAUL BARAJAS
Green Building Final 8/26/2024 Not Ready for Inspection RAUL BARAJAS
HVAC-Final 8/26/2024 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Final 8/26/2024 Not Ready for Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 8/26/2024 SGSOV Not Ready RAUL BARAJAS
Smoke Detectors 8/26/2024 Approved RAUL BARAJAS
Final 9/4/2024 Corrections Issued RAUL BARAJAS
Green Building Final 9/4/2024 Not Ready for Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 9/4/2024 SGSOV Not Ready RAUL BARAJAS
Final 9/9/2024 No Access for Inspection HAMIK HARTOUNIAN
Green Building Final 9/9/2024 No Access for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 9/9/2024 SGSOV Not Ready HAMIK HARTOUNIAN
Final 9/11/2024 Corrections Issued CRAIG VAUGHAN
Green Building Final 9/11/2024 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 9/11/2024 SGSOV Not Ready CRAIG VAUGHAN
Final 9/18/2024 Permit Finaled CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 9/18/2024 SGSOV Approved CRAIG VAUGHAN