8900 S SEPULVEDA BLVD 90045
Certificate Information: 8900 S SEPULVEDA BLVD 90045
- Application / Permit
- 20016-10000-08955
- Plan Check / Job No.
- B20LA06442
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- INTERIOR TENANT IMPROVEMENT FOR A NEW TARGET BUILDING, NO CHANGE OF USE (EXISTING RETAIL BUILDING). WORK INCLUDES INTERIOR NON LOAD BEARING PARTITION WALLS, FLOOR AND CEILING FINISHES. ALL EXTERIOR WORK UNDER PERMIT # 19016 - 10000 - 40802.
- Permit Issued
- Issued on 4/10/2020
- Issuing Office
- Current Status
- Permit Finaled on 12/7/2020
Permit Application Status History
| Submitted | 4/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/6/2020 | RACHEL BEYENE |
| Corrections Issued | 4/6/2020 | RACHEL BEYENE |
| Issued | 4/10/2020 | APPLICANT |
| Building Plans Picked Up | 5/14/2020 | APPLICANT |
| Permit Finaled | 12/7/2020 | ALAN NOVAK |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Cassidy,, David F; Lic. No.: C32857 | REPUBLIC CENTER 1717 PACIFIC AVE. DALLAS, TX 75201 |
| Contractor | Curtom - Dunsmuir A Joint Venture; Lic. No.: 782018-B | 1128 NORTH LA BREA AVENUE INGLEWOOD, CA 90302 |
| Engineer | Fernandez,, Terry Lynn; Lic. No.: S3256 | 1719 CARVER ST REDONDO BEACH, CA 90278 |
Inspector Information
| DANIEL ARMENTA, (310) 914-3925 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/5/2020 | Corrections Issued | ALAN NOVAK |
| Footing/Foundation/Slab | 5/7/2020 | Partial Approval | ALAN NOVAK |
| Footing/Foundation/Slab | 5/20/2020 | Partial Approval | ALAN NOVAK |
| Light Gage Steel Frame | 5/29/2020 | Conditional Approval | ALAN NOVAK |
| Deputy Drilled-In Anchors | 6/1/2020 | Conditional Approval | ALAN NOVAK |
| Light Gage Steel Frame | 6/5/2020 | Partial Approval | ALAN NOVAK |
| Drywall Nailing | 6/10/2020 | Approved | ALAN NOVAK |
| Light Gage Steel Frame | 6/12/2020 | Approved | ALAN NOVAK |
| Drywall Nailing | 6/15/2020 | Approved | ALAN NOVAK |
| Drywall Nailing | 6/22/2020 | Approved | ALAN NOVAK |
| Deputy Drilled-In Anchors | 6/23/2020 | Conditional Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 6/24/2020 | Conditional Approval | ALAN NOVAK |
| Deputy Drilled-In Anchors | 6/29/2020 | Conditional Approval | ALAN NOVAK |
| Drywall Nailing | 7/9/2020 | Partial Approval | ALAN NOVAK |
| Excavation/Setback/Form/Re-Bar | 7/9/2020 | Partial Approval | ALAN NOVAK |
| Light Gage Steel Frame | 7/9/2020 | Partial Approval | ALAN NOVAK |
| Deputy Other (see comments) | 7/13/2020 | Conditional Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 7/13/2020 | Conditional Approval | ALAN NOVAK |
| Deputy Drilled-In Anchors | 7/15/2020 | Conditional Approval | ALAN NOVAK |
| Grading Pre-Inspection | 7/20/2020 | Not Ready for Inspection | ALAN NOVAK |
| Deputy Drilled-In Anchors | 7/24/2020 | Conditional Approval | ALAN NOVAK |
| Deputy Drilled-In Anchors | 7/28/2020 | Conditional Approval | ALAN NOVAK |
| Wood Frame | 8/3/2020 | Partial Approval | ALAN NOVAK |
| Wood Frame | 8/5/2020 | Approved | ALAN NOVAK |
| Deputy Reinf. Concrete | 8/7/2020 | Conditional Approval | ALAN NOVAK |
| Light Gage Steel Frame | 8/14/2020 | Partial Approval | ALAN NOVAK |
| Light Gage Steel Frame | 8/17/2020 | Partial Approval | ALAN NOVAK |
| Light Gage Steel Frame | 8/21/2020 | Partial Approval | ALAN NOVAK |
| Interior/Exterior Lathing | 8/25/2020 | Approved | ALAN NOVAK |
| Light Gage Steel Frame | 8/25/2020 | Approved | ALAN NOVAK |
| Pre-Inspection | 8/27/2020 | Approved | ALAN NOVAK |
| Drywall Nailing | 8/28/2020 | No Result Entered | ALAN NOVAK |
| Drywall Nailing | 8/28/2020 | Off-Hour Fees Due | |
| Drywall Nailing | 8/29/2020 | Approved | ALAN NOVAK |
| Deputy Other (see comments) | 9/4/2020 | Conditional Approval | JONATHAN ALLEN |
| Deputy Reinf. Concrete | 9/4/2020 | Conditional Approval | JONATHAN ALLEN |
| Deputy Reinf. Masonry | 9/10/2020 | Conditional Approval | ALAN NOVAK |
| Final | 9/15/2020 | Off-Hour Fees Due | |
| Green Building Final | 9/15/2020 | Off-Hour Fees Due | |
| SGSOV-Seismic Gas S/O Valve | 9/15/2020 | Off-Hour Fees Due | |
| Smoke Detectors | 9/15/2020 | Off-Hour Fees Due | |
| Pre-Inspection | 9/16/2020 | Approved | ALAN NOVAK |
| T-Bar Ceiling | 9/17/2020 | Pending Review | |
| Pre-Inspection | 9/19/2020 | Approved | ALAN NOVAK |
| SGSOV-Seismic Gas S/O Valve | 10/2/2020 | SGSOV Approved | JOEY BUCHANAN |
| Smoke Detectors | 10/2/2020 | Approved | JOEY BUCHANAN |
| Final | 10/5/2020 | Partial Inspection | ALAN NOVAK |
| Special/Order Compliance | 10/5/2020 | Not Ready for Inspection | NICK LAROCCA |
| Final | 10/7/2020 | Partial Inspection | ALAN NOVAK |
| Pre-Inspection | 10/7/2020 | Pending Review | |
| Final | 10/9/2020 | Not Ready for Inspection | SORIN CIRSTOIU |
| Green Building Final | 10/9/2020 | Not Ready for Inspection | SORIN CIRSTOIU |
| Final | 12/7/2020 | Permit Finaled | ALAN NOVAK |
| Green Building Final | 12/7/2020 | Approved | ALAN NOVAK |